Completing the installation

With the BTS safely fixed to a wall or a pole, commissioning can be started.
Commissioning can be left to a later stage if there are no qualified personnel on
the site during installation. To complete the installation, the BTS cover is fitted to
the chassis and the BTS cabinet is locked.
Commissioning the BTS
1.
2.
3.
Fitting the cover and locking the cabinet
1.
2.
3.
4.
5.
6.
DN991456
© Nokia Corporation
Issue 3 en
Nokia Proprietary and Confidential
All manuals and user guides at all-guides.com
Switch the BTS power ON.
Connect the LMP cable from the MetroSite BTS Manager PC to the LMP
connector on the interface unit.
Proceed to the BTS commissioning tasks. Refer to Nokia MetroSite EDGE
Base Station: Commissioning.
Bring the BTS cover to the BTS chassis (see Figure 27). Attach the safety
strap to the fixing point provided under the top of the cover.
Make sure that the cover is secured with the safety strap (see Figure 27).
Place the cover over the cabinet and align the locking hooks on the cover
to the locking rail on the chassis. Push the cover into the chassis and pull
downwards to lock the hooks firmly into the rail.
Check that the cover is firmly secured by pushing the cover from the sides.
Lock the cabinet with the key.
Clean the site. Recycle any applicable material.
Completing the installation
69 (72)