Connecting A Single-Phase Power Cable - Huawei SmartACBox-12/1-JP User Manual

12-in 1-out smart ac combiner box
Table of Contents

Advertisement

SmartACBox 12-In 1-Out Smart AC Combiner Box
User Manual
Figure 5-9 Connecting an RS485 communications cable
----End

5.7 Connecting a single-phase power cable

Prerequisites
A single-phase power cable and its OT-M4 terminal are available.
Context
The power cables from the SmartACBox to the SmartLogger1000 and router have been
factory-installed. If an external power source is required to power the SmartLogger1000 and
router, disconnect the power cable from the JX02 terminal block, and then connect the
external single-phase power cable to the JX02 terminal block.
Procedure
Step 1 Prepare a single-phase power cable.
Issue 03 (2018-05-15)
Copyright © Huawei Technologies Co., Ltd.