Post-Installation Check; Leak Checking, Vacuuming, And Precharging Refrigerant - Huawei NetCol8000-A Series Quick Manual

In-room air cooled smart cooling product
Hide thumbs Also See for NetCol8000-A Series:
Table of Contents

Advertisement

8

Post-Installation Check

Item
Content
Ports are connected properly. The pipeline has oil traps, inverted U-shaped
traps, gradients (for the refrigerant pipes) , and pipe supports. Pipes are
Refrigerant
securely connected. All pipes are wrapped with thermal insulation foam, and
pipe
the insulation foam is intact. The needle valve plug is secured (torque of
0.45±0.05 N.m) , and valve bonnet is tightened. The pipes have no sharp
bends.
Waterway
Water pipe joints have been sealed. The drainpipe is securely connected.
Cables are not damaged or over-bent. The power cables and outdoor unit
on/off signal cable, water sensor, the teamwork cable, and the T/H sensor
cable are connected as required. The rated specifications of the upstream
Electricity
switch meet the maximum current requirement. All cable connectors are
secured. Indoor and outdoor units are properly grounded.
The cabinet is installed properly, without any tilt. The cabinet should be
Cabinet
secured. The foreign matter inside the cabinet such as cable ties and cable
cuts is cleaned up.
Compressor The transport fasteners of the compressor are removed. The bolts on the
compressor are tightened.
The air filter is correctly installed according to the airflow direction marked on
Air filter
the frame.
The fan blades do not interfere and protective cardboard for fins are
removed. Bonnets of needle valves and water-proof connectors are
Outdoor unit
tightened. Cables are protected by tubes and the cable outlet faces
downward. Glue is applied to the waterproof connector when the outdoor unit
is placed vertically and the waterproof connector faces upward.
9

Leak Checking, Vacuuming, and Precharging Refrigerant

9.1
Leak Checking
Charge 3.0 MPa nitrogen and preserve the system for 24 hours. If the ambient temperatures before
and after the preservation are similar, the system pressure should not drop. If leaks occur after the
preservation, check them along the pipe, especially at the welding positions, needle valve, and angle
valve.
9.2
Vacuuming
The vacuuming time should be 80 minutes at least and the final pressure (absolute pressure) should
be 60 Pa at most. When the pressure stops dropping, pump for another 10 minutes. After the
vacuumization, close all the vacuum pump and valves. Preserve the system for another 10 minutes
and the pressure (absolute pressure) should be 90 Pa at most. If the pressure gauge cannot be
precise at 60 Pa, ensure that the pressure is displayed at the minimum scale. Extend the preservation
time to one hour. Then check whether the pressure displayed on the pressure gauge increases.
9.3
Precharging Refrigerant
1. Remove the vacuum pump from the vacuuming equipment, and replace the vacuum pump with a
refrigerant steel vessel.
2. Partially open the refrigerant steel vessel valve and rubber tube nut. Tighten the nut when you feel
cold air coming out from the nut.
3. Put the refrigerant steel vessel upside down on an electric balance. Clear the reading on the
balance.
4. Open pressure gauge valves, and the refrigerant steel vessel valve to charge refrigerant.
5. The amount of refrigerant charged must be more than half of the total charge amount calculated
and less than the total charge amount. Charge the remaining refrigerant during power-on
commissioning.
6. After refrigerant charging, close pressure gauge valves, and the refrigerant steel vessel valve.
25
Result
□Passed
□Failed
□Passed
□Failed
□Passed
□Failed
□Passed
□Failed
□Passed
□Failed
□Passed
□Failed
□Passed
□Failed