UPS5000-(200 kVA-800 kVA) Top Air-flow Cabinet
User Manual
Before installation, ensure that the UPS has completely powered off and that the UPS input
and output power cables and battery cables are disconnected. During installation, wear
insulation gloves.
3.3.1 Securing the Top Air-flow Cabinet Used for a
Single-Cabinet UPS
Prerequisites
Procedure
Step 1 Remove the rear cover from the UPS cabinet.
Issue Draft A (2016-12-09)
Before installing the top air-flow cabinet, ensure that the UPS anchor bolts have been
adjusted.
If the UPS is to be installed against a wall, combine the top air-flow cabinet with the UPS
and then move them to the installation position. If the antiseismic kit is configured, secure
it to the UPS first.