4
PROCEDURES BEFORE OPERATION
This chapter describes the procedures before operation.
1.
Network construction
Configure the system and set the parameters which are required for start-up.
• Wiring (Page 35 WIRING)
• Parameter Setting ( MELSEC iQ-R CC-Link IE TSN User's Manual (Application))
2.
Network diagnostics
Using CC-Link IE TSN/CC-Link IE Field diagnostics, check if the cables are connected properly and communication is
performed normally with the configured parameters.
For details, refer to the following.
MELSEC iQ-R CC-Link IE TSN User's Manual (Application)
3.
Programming
Create a program. For details, refer to the following.
Page 38 COMMUNICATION EXAMPLES
4 PROCEDURES BEFORE OPERATION