6.1 Checking Before Power-On

Table 6-1 Installation checklist
No.
1
2
3
4
5
6
7
8
9
Issue 01 (2018-08-30)
6
Check Item
SUN2000 installation
Installation of the WiFi
antenna or 4G module
Cable layout
Cable tie
Grounding
DC switch
Cable connections
Unused terminals and ports
Installation environment
Copyright © Huawei Technologies Co., Ltd.

System Commissioning

Acceptance Criteria
The SUN2000 is installed correctly,
securely, and reliably.
The WiFi antenna or 4G module is installed
correctly, securely, and reliably.
Cables are routed properly as required by the
customer.
Cable ties are secured evenly and no burr
exists.
The ground cable is connected correctly,
securely, and reliably.
The DC switch and all the switches
connecting to the SUN2000 are OFF.
The AC output power cable, DC input power
cable, and signal cable are connected
correctly, securely, and reliably.
Unused terminals and ports are locked by
watertight caps.
The installation space is proper, and the
installation environment is clean and tidy,
without foreign matter.