3.5.3 Reverse RSSI Test

The RSSI test includes the local RSSI test and the remote RSSI test.
In the case of the remote RSSI test, you can perform the reverse RSSI test by:
In the case of local RSSI test, you can connect the WS to the BCKM by using a crossover
Ethernet cable and then log in to the BTS in Telnet mode. In this mode, you can use
commands to perform BTS commissioning.
This section describes how to conduct reverse RSSI tests in the local RSSI test. It also
describes the precautions you must take when conducting the tests.
Precautions
Note the following points before conducting the forward power test:
Test Procedure
The test procedure is as follows:
Step 1 Connect the cables as shown in Figure 3-9.

Figure 3-9 Connection for reverse RSSI test of the BTS

Network
Issue 02 (2006-10-10)
If Base band power is normal, but Digital power is not normal, the values of HPA
Output power must be not normal in theory. In such a case, check the CMTR or OMTR
to locate the fault. For example, insert and remove it, or replace it.
If only HPA Output power is not normal, check the installation of CMPA or OMPA and
its connection with the CMTR or OMTR.
If all the parameter values reported in the interface tracing are normal, do as follows:
Check the connections between the CMPA/OMPA and the CDDU/IDFU/ODFU.
Check the antenna system and ports on the top of the cabinet for errors.
Selecting Resource Monitoring > RSSI Monitoring, or
Logging in to the BTS in Telnet mode.
You can choose not to install RF fans; however, to ensure zero transmission power, you
have to connect the antenna with the CDDU/CDFU.
The unit for the average and peak values of RSSI is 0.1 dBm.
Check whether the coupling port without connection lines is connected to a matching
load to avoid generating internal interference and external radiation.
port
Crossover cable
BCKM
BTS
Huawei Technologies Proprietary
3 Commissioning Process
3-25

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Airbridge bts3606ae

Table of Contents