4.4 Custom Schedules and Quick Clean

To customize the run schedule for your Variable
Speed Pump, the pump must be stopped. Be sure that
the Start/Stop button LED is not illuminated.
Programming a Custom Schedule:
Note: When programming, the LED light next to
the parameter ("Speed", "Time," and "Duration") you are
setting will blink.
1. Stop the pump if it is running by pressing the Start/Stop
button.
2. Press the "1" button. The LED above the selected SPEED
will begin to blink and the "Speed" parameter LED will
blink while editing. See Figure 5.
Figure 5: Setting Speed
3. Use the "+" and "-" arrows to adjust the speed in RPM for
SPEED 1.
Note: Speed is adjusted up or down by increments
of 10 RPM.
4. Press the "1" button again and the display will change to
SPEED 1 start time. The "Time" parameter
LED will begin to blink. See Figure 6.
Figure 6: Setting Start Time
5. Use the "+" and "-" arrows to adjust the daily start time for
SPEED 1.
ENGLISH
6. Press the "1" button again and the display will change to
SPEED 1 duration. The "Duration" parameter LED will
begin to blink. See Figure 7.
Figure 7: Setting Duration
7. Use the "+" and "-" arrows to adjust the duration for
SPEED 1 in hours and minutes.
Note: The duration parameter is adjusted in 15
minute increments.
8. Pressing the "1" button will continue to cycle through
these parameters, but the changes are immediately
saved as they are adjusted.
9. Press the "2" button. The LED above SPEED 2 will begin
to flash and the corresponding parameter LED will flash
while editing.
Use the "+" and "-" arrows to adjust the speed in RPM for
10.
SPEED 2.
11.
Press the "2" button again and the display will change to
SPEED 2 duration.
Note: SPEEDs 2 and 3 do not have a start time, as they
begin their duration immediately after the previous
SPEED finishes.
Use the "+" and "-" arrows to adjust the duration for
12.
SPEED 2 in hours and minutes.
Repeat steps 9-12 to program SPEED 3-4 and QUICK
13.
CLEAN.
Note: Remember that the duration allowed for SPEED 3
will be limited to the remaining time in a 24 hour day. Any
time in the 24 hour day not programmed into SPEEDs
1-4, the pump will remain in a stationary state.
[ SPEED 1 + SPEED 2 + SPEED 3 + SPEED 4 < 24 Hours ]
14. Press the Start/Stop button and ensure the LED is
lit. The pump is now on and will run the custom
user-programmed schedule.
Installation & Operation Manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bdxbtvar200Bdxbtvar300

Table of Contents