Sf6 circuit- breaker
Table of Contents

Advertisement

Installation
04- 2017
Content
Instruction Manual
Erection general instructions
Tightening torques
Erection general procedures
Checking for presence of nitrogen (N
The installation procedure (advised), developed
below, imposes a lifting equipment with the following
characteristics :
NOTE : If it is impossible to obtain the advoca-
ted lifting equipment, one "complementary instal-
lation procedure" is supplied in annexes.
Support- frame assembly
Column - chambers coupling
Tipping down the pole of the circuit- breaker
and vacuum operation
Installing terminals with preparation of contact
surfaces
Installing the capacitors
Lifting and positionning the pole
Installing the operating device
GE Information
L30- 002EN/03
L31- 001EN/03
L31- 003EN/03
L31- 064EN/05
) in pole parts
2
H + 2 m
H
L31- 139EN/03
L31- 7142EN/02
L31- 722EN/03
L31- 736EN/03
L31- 742EN/03
L31- 766EN/07
L31- 7902EN/02
Continued on next page.
3,000 daN)
(minimum)
H + 1 m
D2021EN/01
6/10