GE GL317D Instruction Manual page 267

Sf6 circuit- breaker
Table of Contents

Advertisement

Presentation
Markings
Time taken for
coupling operation
Lifting means
Stages of the
coupling operation
03- 2017
Installation
Chamber - Column Coupling
Before coupling the chambers and column, check that the markings on the
breaking chambers correspond with those on the column
The final chamber/column coupling operations should be completed in a
time of  40 min.
NOTE:
The coupling operations must be carried out by a minimum
of two people.
T(max)  40 min
Provide an adequate means of
hoisting:
3,000 daN (minimum).
An aerial basket is mandatory.
The chamber- column coupling operation can be broken down into a num-
ber of stages:
Step
A
Checking of the insertion resistor
B
Preparing the column's corona shield
Preparing the elements required for the coupling opera-
C
tion
D
Hoisting and preparing the breaking chamber
Final coupling
E
GE Information
H + 2 m
H
Subject
Page
2
3
4
6
7
L31- 7143EN/02