Final Checkout Setup; Figure 5-1 Cabinet Breaker Panel For Standard Site Controller Rack Or - Motorola iDEN Site Controller System Manual

Gen 3
Table of Contents

Advertisement

Chapter 5 Final Checkout

Final Checkout Setup

Final Checkout Setup
Figure 5-1
Cabinet Breaker Panel for standard site
controller rack or SRRC (front view)
5-2
The following procedures should be performed after installation of the site
controller is complete. This Final Checkout procedure ensures the proper
operation of the site controller.
On the Cabinet, set all circuit breakers to OFF.
1.
Figure 5-1 shows the Cabinet Breaker Panel.
BR1
BR3
ON
ON
OFF
OFF
OFF
OFF
25A
25A
For details of the AC/DC Power System for the SRSC, refer to the SRSC
GEN 4 EBTS section of the EBTS System Manual. (on CD: 98P80800A17)
Gen 3 Site Controller System Manual
RFS1
RFS3
CTRL A
BR2
BR4
ON
ON
ON
ON
ON
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
3A
3A
7.5A
25A
25A
RFS2
EAS/IMU CTRL B
ON
ON
ON
ON
OFF
OFF
OFF
OFF
OFF
OFF
OFF
3A
7.5A
7.5A
iSC076
060796JNM
68P80801E30-A 5/1/2002

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents