22.4
Initial commissioning of additional devices
Normally, the device has already been commissioned by the machine manufacturer. If an initial
commissioning has not been performed or if, for example, function tests are to be performed
again (e.g. when retrofitting additional devices), this is possible at any time.
The "Start-up" softkey has been declared as Manufacturer data class (M).
Procedure
Milling
Operating Manual, 05/2017, A5E40868956
1.
Select the "Parameter" operating area.
2.
Press the menu forward key and then the "Easy Extend" softkey.
3.
Press the "Start-up" softkey.
A new vertical softkey bar appears.
4.
Press the "Comm. start-up" softkey to start the commissioning.
Before starting, a complete data backup is generated which you can then
use in case of an emergency.
5.
Press the "Cancel" softkey if you want to abort the commissioning pre‐
maturely.
6.
Press the "Restore" softkey to load the original data.
7.
Press the "Device function test" softkey to test the machine manufactur‐
er's intended function.
Easy Extend (828D only)
22.4 Initial commissioning of additional devices
813