Mitsubishi Electric MELSEC iQ-R Series Programming Manual page 141

Process control function blocks
Hide thumbs Also See for MELSEC iQ-R Series:
Table of Contents

Advertisement

• Changing nine or more bit ON/OFF duty output phases
If multiple P_DUTY_8PT_ function blocks are connected, nine or more bit ON/OFF duty output phases can be changed.
When connecting multiple P_DUTY_8PT_ function blocks, connect LINKOUT of the preceding FB with LINKIN of the
following FB, set PRIMARY of the preceding FB to TRUE, and PRIMARY of the following FB to FALSE. The value of CTDUTY
and DELAY of the first FB is applied to the value of CTDUTY and DELAY of the following FB.
Ex.
Execution cycle: T: 100ms
• First FB
Control output cycle: CTDUTY = 2.0s
Input: MV0 = 40%, MV1 = 20%, MV2 = 40%, MV3 = 15%, MV4 = 30%, MV5 = 100%, MV6 = 0%, MV7 = 35%
Output ON delay time: DELAY = 0.1s
Lead FB specified: PRIMARY = TRUE
• Second FB
Control output cycle: CTDUTY = Same as CTDUTY of the preceding FB (2.0s in this example)
Input: MV0 = 25%
Output ON delay time: DELAY = Same as DELAY of the preceding FB (0.1s in this example)
Start FB specification: PRIMARY = FALSE
Control output
cycle
(CTDUTY)
Execution cycle
(ΔT)
100ms
MVB0
800ms
MVB1
MVB2
200ms
MVB3
300ms
MVB4
MVB5
MVB6
DELAY
MVB7
200ms
MVB0
2s
DELAY
400ms
600ms
2000ms
500ms
600ms
500ms
8.11 8 Points Time Proportional Output (M+P_DUTY_8PT_)
1st step FB
2nd step FB
8 CONTROL OPERATION