UPS5000-H-(400 kVA-800 kVA)
User Manual (100 kVA Power Module)
Figure 6-11 Recommended channel steel dimensions (unit: mm)

6.3.1.2 Installing Cables

Context
Procedure
Step 1 Open the front door of the cabinet, remove the power distribution cover, and
remove the top cover as required.
Figure 6-12 Removing the covers
Step 2 Install ground cables.
Issue 02 (2021-04-22)
NO TE
The number and colors of cables in the figures are for reference only.
Copyright © Huawei Technologies Co., Ltd.
6 Installation
71