1.
Install the new fuse block as follows:
For 2018 and before machines, snap the
new fuse block onto the existing fuse block
on the machine
For 2019 and after machines, secure the
new fuse block using the 2 self-tapping
screws as shown in
Figure 21
1. Self-tapping screw
2.
Connect the large connector on the new fuse
block to the optional power cable on the existing
fuse block
(Figure
3.
Route the wire harness behind the cab and
under the seat, and secure the clip on the wire
harness to the side panel
(Figure
17).
Figure
21.
2. New fuse block
17).
(Figure
19).
4.
Install the black terminal ring to the ground block
on the machine
5.
Install the red power wire into an empty slot on
the machine fuse block
Note:
Install an additional fuse block if there
are no remaining slots open in a fuse block.
g290831
1. Cab wire harness
2. Black ground wire with
terminal ring
6.
Connect the remaining wire to the fused wire on
the new fuse block
7.
Lower the bed and connect the battery; refer to
the Operator's Manual.
8.
Install the previously removed seat base.
14
(Figure
22).
(Figure
22).
Figure 22
3. Black ground wire with
spade terminal
4. Red power wire with spade
terminal
(Figure
17).
g278776

Advertisement

Table of Contents
loading

This manual is also suitable for:

07142

Table of Contents