13. OUTDOOR INSTALLATION
13-3. Piping direction
13-3-1. Lifting method
• Always use two slings to lift up the unit. Each sling must be at least 8 m (26 ft) long and must be able to support the weight
of the unit.
• Put protective pads between slings and the unit where the slings touch the unit at the base to protect the unit from being
scratched.
• Put 50 mm (2 in) or thicker protective pads between slings and the unit where the slings touch the unit at the top of the unit
to protect the unit from being scratched and to avoid contact with the slings and the fan guard.
• Make sure that the angles between slings at the top are less than 40 degrees
HP72, 96, 120
Slings
(Min. 8m [26 ft.] × 2)
Protective pads
(Minimum thickness:
50 mm (2 in))
(two each in the
front and back)
Protective pads
(two each in the
front and back)
CAUTION
Exercise caution when transporting products.
· Products weighing more than 20 kg [45 LBS] should not be carried alone.
· Do not carry the product by the PPbands.
· To avoid the risk of injury, do not touch the heat exchanger fins.
· Plastic bags may pose a risk of choking hazard to children. Tear plastic bags into pieces before disposing of them.
· When lifting and transporting outdoor units with ropes, run the ropes through lifting hole at the unit base. Securely
fix the unit so that the ropes will not slide off, and always lift the unit at four points to prevent the unit from falling.
MEES19K180
≤40°
Fan guard
Sling holes
(two each in the front and back)