Chapter 2. Installing the Pipe Nozzles

2.3.6 Installing the Second Welding Boss and Nozzle MR1 Mid-Radius

Install the second welding boss and nozzle at the marked position (see Figure 43 below) as described in "Installing the
First Welding Boss - MR1 Mid-Radius" on page 29 and "Installing the First Nozzle - MR1 Mid-Radius" on page 32.
Top View
Figure 43: Installing the Second Welding Boss and Nozzle
The completed installation should appear as shown in Figure 44 below.
Nozzle (2 places)
Welding Boss (2 places)
45º
Flow
Top View
End View
Figure 44: Completed MR1 Mid-Radius Installation