Installing a Return Air Duct
The return air duct needs to be prepared onsite.
Use five screws (M6 x 12) to secure the
horizontal board and use three screws (M6 x 12)
to secure the vertical board.
Dimensions of reserved holes for device
Unit: mm
6
Connecting Cables
6.1
Connecting Power Cables and Signal Cables
1. All power cables and ground cables must
comply with local national standards.
2. For details about electrical ports, see the
FusionCol8000-E400 Modular Indirect
Evaporative Cooling System User Manual.
3. After connecting power cables and checking
cable connections, use sealing putty to fill in
the gap between the cables and the cabinet
(as shown in the right figure), and the sealing
putty can be obtained from the fitting bag.
(1) Paper protective film
7
(2) Sealing putty