Figure 5-29 Preparing a cable terminal outside the cabinet
Step 4 Connect the cable with a crimped terminal to the corresponding copper bar.
Step 5 Clean foreign matter inside the cabinet.
----End

5.4.4.1 Top Cable Routing

The following procedure applies to a dual-input PDC.
Procedure
Step 1 Remove the rodent-proof meshes at the top and put them aside.
Figure 5-30 Removing rodent-proof meshes at the top
Step 2 Remove the transparent covers of the N bar and input copper bar, and put the covers aside.
Issue 03 (2018-01-25)
Choose an appropriate cabling route based on the actual situation. The figure is for reference only.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installation Guide