Installing The Pdc On An Esd Floor - Huawei PDU8000 Series User Manual

Modular precision pdc v2.0
Hide thumbs Also See for PDU8000 Series:
Table of Contents

Advertisement

PDU8000 Modular Precision PDC V2.0
User Manual

5.3.3 Installing the PDC on an ESD Floor

Context
A support is required when the PDC is installed on an ESD floor. The support height depends
on the height between the ground and the ESD floor.
Procedure
Step 1 Lower the leveling feet of the PDC using an adjustable wrench until all castors are off the
ground and the cabinet is level.
Step 2 Lift the PDC onto the support and align the mounting holes in the PDC with those in the
support.
Step 3 Level the PDC by adjusting the leveling feet.
Figure 5-10 Leveling PDC
(1) Leveling foot
Step 4 Insert four M12 bolts into the mounting holes in the PDC and support, and partially tighten
the bolts.
Issue 03 (2018-01-25)
Scenario 1
Figure 5-11 Securing the cabinet
Scenario 2
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installation Guide
(2) Level
42

Advertisement

Table of Contents
loading