6.3

Wiring of CC-Link IE Field Network

This section describes the wiring when CC-Link IE Field Network is used.
Wiring methods
The following describes connection and disconnection of the Ethernet cable.
■Connecting the cable
1.
Push the Ethernet cable connector into the CC-Link IE Field Network-equipped master/local module until it clicks. Pay
attention to the connector's direction.
2.
Lightly pull it to check that it is securely connected.
3.
Check whether the LINK LED of the port connected with an Ethernet cable is on.
*1 The time between the cable connection and the LINK LED turning on may vary. The LINK LED usually turns on in a few seconds. Note,
however, that the time may be extended further if the link-up processing is repeated depending on the status of the device on the line. If
the LINK LED does not turn on, refer to the following and take corrective actions.
 MELSEC iQ-R CC-Link IE Field Network User's Manual (Application)
Both P1 connector and P2 connector can be used. (For the RJ71EN71 and the RnENCPU (network part), ring
topology is available only when "CC-Link IE Field" is selected as network type for P1 connector.)
• When only one connector is used in star topology, either P1 connector or P2 connector is applicable.
• When two connectors are used in line topology and ring topology, the cable can be connected between P1
and P1, P2 and P2, or between P1 and P2.
■Disconnecting the cable
1.
Press the latch down and unplug the Ethernet cable.
*1
6 WIRING
6.3 Wiring of CC-Link IE Field Network
6
67