Step 7 Set the SNMP trap destination address and trap port.
Step 8 Upload the MIB libraries HUAWEI-MIB.mib and HUAWEI-SITE-MONITOR-MIB.mib
to the NMS.
----End

6.9 Connecting the Battery Supply

Prerequisites
To avoid damage to batteries, switch on the battery circuit breaker only after correctly setting
the battery parameters.
Procedure
Step 1 Switch off the AC circuit breaker for the upper-level device, and then switch on the battery
circuit breaker on PDU.
Step 2 Switch on the AC circuit breaker for the upper-level device, and then switch on the load
circuit breakers on PDU.