Testing The Energizing Check - ABB rec670 Commissioning Manual

Intelligent electronic device
Hide thumbs Also See for rec670:
Table of Contents

Advertisement

Section 10
Testing functionality by secondary injection
10.9.1.3
146
The voltage difference between the voltage connected to U-Bus and U-Line
should be 0%, so that the AUTOSYOK and MANSYOK outputs are activated
first.
2.
Change the U-Line voltage connection to U-Line2 without changing the setting
on the local HMI. Check that the two outputs are not activated.

Testing the energizing check

During the test of the energizing check function for a single bay arrangement, these
voltage inputs are used:
U-Line
UL1, UL2 or UL3 line1 voltage inputs on the IED
U-Bus
Bus voltage input on the IED
General
When testing the energizing check function for the applicable bus, arrangement shall
be done for the energizing check functions. The voltage is selected by activation of
different inputs in the voltage selection logic.
Live voltage level is fixed to 80% UBase and dead voltage level to fixed 40% UBase.
The test shall be performed according to the settings for the station. Test the
alternatives below that are applicable.
Testing the dead line live bus (DLLB)
The test should verify that the energizing check function operates for a low voltage on
the U-Line and for a high voltage on the U-Bus. This corresponds to the energizing of
a dead line to a live bus.
1.
Apply a single-phase voltage 100% GblBaseSelBus to the U-Bus, and a single-
phase voltage 30% GblBaseSelLine to the U-Line.
2.
Check that the AUTOENOK and MANENOK outputs are activated after set
tAutoEnerg respectively tManEnerg.
3.
Increase the U-Line to 60% GblBaseSelLine and U-Bus to be equal to 100%
GblBaseSelBus. The outputs should not be activated.
4.
The test can be repeated with different values on the U-Bus and the U-Line.
Testing the dead bus live line (DBLL)
The test should verify that the energizing check function operates for a low voltage on
the U-Bus and for a high voltage on the U-Line. This corresponds to an energizing of
a dead bus to a live line.
1MRK 511 360-UEN A
Bay control REC670 2.1 IEC
Commissioning manual