Starting up
4.3
4.4
4.4.1
42
PC with PCM600 installed along with the connectivity packages corresponding
to the IEDs to be tested.
Administration rights on the PC, to set up IP addresses
Product documentation (engineering manual, installation manual,
commissioning manual, operation manual, technical manual and communication
protocol manual)

Checking the power supply

Do not insert anything else to the female connector but the
corresponding male connector. Inserting anything else (such as a
measurement probe) may damage the female connector and prevent a
proper electrical contact between the printed circuit board and the
external wiring connected to the screw terminal block.
Check that the auxiliary supply voltage remains within the permissible input voltage
range under all operating conditions. Check that the polarity is correct before

energizing the IED.

Energizing the IED

Checking the IED operation

Check all connections to external circuitry to ensure correct installation, before
energizing the IED and carrying out the commissioning procedures.
Energize the power supply of the IED to start it up. Keep the DC power supply on until
the Root menu or the selected default screen is shown on the HMI before interrupting
the DC power supply again. The energization could be done in a number of ways, from
energizing a whole cubicle with many IEDs to energizing each single IED one by one.
If HW (i.e. I/O and/or communication boards etc.) have been changed (i.e. removed,
replaced, or added), the user should re-configure the IED by navigating in the local
HMI menu to: Main menu/Configuration/Reconfigure HW modules to activate
the changed hardware modules in order to enable the self-supervision function to
detect possible hardware errors.
Check also the self-supervision function in Main menu/Diagnostics/IED status/
General menu in local HMI to verify that the IED operates properly.
Set the IED time if no time synchronization source is configured.
To ensure that the IED is according to the delivery and ordering specifications
documents delivered together with each IED, the user should also after start-up use the
built in HMI to check the IED's:
1MRK 511 360-UEN A
Bay control REC670 2.1 IEC
Commissioning manual