Huawei AP3010DN-AGN Hardware Installation And Maintenance Manual page 52

Hide thumbs Also See for AP3010DN-AGN:
Table of Contents

Advertisement

Huawei AP3x10xN&5x10xN&5x30xN&6x10xN&7x10xN
Hardware Installation and Maintenance Guide
Figure 5-10 Heating the heat shrink tubing (JG terminal)
----End
Assembling the Cord End Terminal and the Power Cable
Context
Figure 5-11
Figure 5-11 Components of a cord end terminal and a power cable
A. Cord end terminal
Procedure
Step 1 Based on the cross-sectional area of the cable conductor, strip a part of the insulation. The L1-
long conductor is exposed, as shown in
in
Table
Issue 11 (2015-05-18)
shows the components of a cord end terminal and a power cable.
B. Insulation layer of a power cable
5-3.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
C. Conductor of a power cable
Figure
5-12. The recommended values of L1 are listed
5 Appendix
45