Hitachi Relion 670 Series Commissioning Manual page 8

Line distance protection
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

Table of contents
4.10
Checking the binary input/output circuits...................................................................................49
4.10.1
Binary input circuits................................................................................................................. 49
4.10.2
Binary output circuits............................................................................................................... 49
4.11
Checking optical connections....................................................................................................49
Section 5
Configuring the IED and changing settings................................................... 51
5.1
Overview................................................................................................................................... 51
5.2
Configuring analog CT inputs....................................................................................................51
5.3
Supervision of input/output modules......................................................................................... 52
Section 6
6.1
Entering settings........................................................................................................................53
6.1.1
Entering SPA settings..............................................................................................................53
6.1.2
Entering IEC settings...............................................................................................................53
6.2
Verifying the communication..................................................................................................... 53
6.2.1
Verifying SPA communication..................................................................................................54
6.2.2
Verifying IEC communication.................................................................................................. 54
6.3
Fiber optic loop..........................................................................................................................54
6.4
Optical budget calculation for serial communication with SPA/IEC .......................................... 55
Section 7
7.1
Communication via the rear ports ............................................................................................ 57
7.1.1
LON communication................................................................................................................57
7.1.2
The LON Protocol....................................................................................................................58
7.1.3
Hardware and software modules.............................................................................................58
7.2
Optical budget calculation for serial communication with LON ................................................ 60
Section 8
8.1
Overview................................................................................................................................... 61
8.2
Setting the station communication............................................................................................ 61
8.3
Verifying the communication .................................................................................................... 61
Section 9
communication................................................................................................. 63
9.1
Overview................................................................................................................................... 63
9.2
Setting the PMU station communication (PMU Report)............................................................ 63
9.3
Setting the PMU station communication (PMU configuration).................................................. 63
9.4
Setting the TCP/UDP client communication..............................................................................64
9.5
Verifying the communication..................................................................................................... 67
9.5.1
Verifying the IEEE C37.118/1344 TCP communication...........................................................67
9.5.2
Verifying the IEEE C37.118/1344 UDP communication.......................................................... 73
9.6
Optical budget calculation for PMU - PDC communication....................................................... 74
Section 10
Testing IED operation....................................................................................... 75
10.1
Preparing for test.......................................................................................................................75
2
© 2017 - 2023 Hitachi Energy. All rights reserved
1MRK506371-UUS Rev. M
Line distance protection REL670
Commissioning manual