Table of Contents

Advertisement

Quick Links

®
Relion
670 SERIES
Transformer protection RET670
Version 2.2 IEC
Commissioning manual

Advertisement

Table of Contents
loading

Summary of Contents for Hitachi RET670

  • Page 1 ® Relion 670 SERIES Transformer protection RET670 Version 2.2 IEC Commissioning manual...
  • Page 3 Document ID: 1MRK 504 165-UEN Issued: July 2022 Revision: K Product version: 2.2 © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 4 Copyright This document and parts thereof must not be reproduced or copied without written permission from Hitachi Energy, and the contents thereof must not be imparted to a third party, nor used for any unauthorized purpose. The software and hardware described in this document is furnished under a license and may be used or disclosed only in accordance with the terms of such license.
  • Page 5 This document has been carefully checked by Hitachi Energy but deviations cannot be completely ruled out. In case any errors are detected, the reader is kindly requested to notify the manufacturer.
  • Page 6 Directive 2004/108/EC) and concerning electrical equipment for use within specified voltage limits (Low-voltage directive 2006/95/EC). This conformity is the result of tests conducted by Hitachi Energy in accordance with the product standard EN 60255-26 for the EMC directive, and with the product standards EN 60255-1 and EN 60255-27 for the low voltage directive.
  • Page 7: Table Of Contents

    Using the RTXP test switch ....................52 4.10 Checking the binary input/output circuits................53 4.10.1 Binary input circuits......................53 4.10.2 Binary output circuits......................53 4.11 Checking optical connections....................53 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 8 Preparing the connection to the test equipment..............81 10.4 Connecting the test equipment to the IED................82 10.5 Releasing the function to be tested..................82 10.6 Verifying analog primary and secondary measurement............83 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 9 Verifying the three-phase pickup from winding two side..........99 11.3.5.7 Verifying the single-phase pickup from winding two side........... 100 11.3.5.8 Verifying the operate characteristic................101 11.3.5.9 Completing the test....................102 11.4 Impedance protection......................102 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 10 Checking the underreaching zone................134 11.4.10.5 Completing the test....................134 11.4.11 Pole slip protection PSPPPAM..................134 11.4.11.1 Verifying the settings....................134 11.4.11.2 Completing the test....................137 11.4.12 Out-of-step protection OOSPPAM ..................137 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 11 Sensitive directional residual overcurrent and power protection SDEPSDE ....164 11.5.6.1 Measuring the operate and time limit for set values...........165 11.5.6.2 Completing the test....................169 11.5.7 Thermal overload protection, one time constant, Celsius/Fahrenheit LCPTTR/LFPTTR169 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 12 Capacitor bank protection CBPGAPC................182 11.5.16.1 Verifying the settings and operation of the function........... 182 11.5.16.2 Completing the test....................185 11.5.17 Negative-sequence time overcurrent protection for machines NS2PTOC ..... 185 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 13 Phase voltage differential based capacitor bank unbalanced protection, SCPDPTOV...209 11.7.3.1 Verifying the signals and settings................209 11.7.3.2 Completing the test....................215 11.7.4 Voltage unbalance protection of shunt capacitor bank, SCUVPTOV......215 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 14 11.10.6.1 Verifying the signals and settings................228 11.10.6.2 Completing the test....................229 11.11 Control..........................229 11.11.1 Synchrocheck, energizing check, and synchronizing SESRSYN........229 11.11.1.1 Testing the synchronizing function................230 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 15 Current reversal and Weak-end infeed logic for distance protection 3-phase ZCRWPSCH ........................253 11.12.3.1 Function revision history.................... 254 11.12.3.2 Current reversal logic....................254 11.12.3.3 Weak end infeed logic....................254 11.12.3.4 Completing the test....................255 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 16 Verifying the signals and settings................268 11.14.7.2 Completing the test....................269 11.14.8 Function revision history....................269 11.14.9 Current harmonic monitoring CHMMHAI.................269 11.14.9.1 Verifying the signals and settings................269 11.14.9.2 Completing the test....................270 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 17 Commissioning and maintenance of the fault clearing system....287 14.1 Commissioning tests......................287 14.2 Periodic maintenance tests....................287 14.2.1 Visual inspection......................288 14.2.2 Maintenance tests......................288 14.2.2.1 Preparation.........................288 14.2.2.2 Recording........................288 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 18 15.2.3 Diagnosing the IED status via the LHMI hint menu............294 15.2.4 Hardware re-configuration....................297 15.3 Repair instruction......................298 15.4 Repair support........................299 15.5 Maintenance........................299 Section 16 Glossary..................... 301 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 19: Introduction

    The commissioning personnel must have a basic knowledge of handling electronic equipment. The commissioning and maintenance personnel must be well experienced in using protection equipment, test equipment, protection functions and the configured functional logics in the IED. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 20: Product Documentation

    IED. The manual also describes how to identify disturbances and how to view calculated and measured power grid data to determine the cause of a fault. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 21: Document Revision History

    ZMFCPDIS, SAPTUF, STBPTOC, CHMMHAI, VHMMHAI, OC4PTOC, EF4PTOC, NS4PTOC, SCCFPVOC, DRPRDRE, SXSWI and SXCBR. 2022-07 2.2.5.4 Introduced RIA600, which is a software implementation of the IED LHMI panel. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 22: Related Documents

    The caution hot surface icon indicates important information or warning about the temperature of product surfaces. Class 1 Laser product. Take adequate measures to protect the eyes and do not view directly with optical instruments. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 23: Document Conventions

    Function block name Edition 1 logical nodes Edition 2 logical nodes ALGOS ALSVS AGSAL AGSAL AGSAL SECLLN0 ALMCALH ALMCALH ALMCALH ALTIM ALTIM Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 24 FDPSPDIS FDPSPDIS FLTMMXU FMPSPDIS FMPSPDIS FMPSPDIS FRPSPDIS FPSRPDIS FPSRPDIS FUFSPVC SDDRFUF FUFSPVC SDDSPVC GOPPDOP GOPPDOP GOPPDOP PH1PTRC GUPPDUP GUPPDUP GUPPDUP PH1PTRC Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 25 QCRSV QCRSV QCRSV RCHLCCH RCHLCCH RCHLCCH REFPDIF REFPDIF REFPDIF ROV2PTOV GEN2LLN0 PH1PTRC PH1PTRC ROV2PTOV ROV2PTOV SAPFRC SAPFRC SAPFRC SAPTOF SAPTOF SAPTOF Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 26 TCMYLTC TCMYLTC TEIGAPC TEIGGIO TEIGAPC TEIGGIO TEILGAPC TEILGGIO TEILGAPC TMAGAPC TMAGGIO TMAGAPC TR1ATCC TR1ATCC TR1ATCC TR8ATCC TR8ATCC TR8ATCC TRPTTR TRPTTR TRPTTR Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 27 ZMHPDIS ZMMAPDIS ZMMAPDIS ZMMAPDIS ZMMPDIS ZMMPDIS ZMMPDIS ZMQAPDIS ZMQAPDIS ZMQAPDIS ZMQPDIS ZMQPDIS ZMQPDIS ZMRAPDIS ZMRAPDIS ZMRAPDIS ZMRPDIS ZMRPDIS ZMRPDIS ZMBURPSB ZMBURPSB ZMBURPSB ZPCPSCH ZSMGAPC ZSMGAPC ZSMGAPC Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 29: Safety Information

    Never connect or disconnect a wire and/or a connector to or from a IED during normal operation. Hazardous voltages and currents are present that may be lethal. Operation may be disrupted and IED and measuring circuitry may be damaged. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 30: Caution Signs

    M2695-2 v2 Always transport PCBs (modules) using certified conductive bags. M2696-2 v1 Do not connect live wires to the IED. Internal circuitry may be damaged Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 31: Note Signs

    Note signs IP1497-1 v1 M19-2 v3 Observe the maximum allowed continuous current for the different current transformer inputs of the IED. See technical data. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 33: Available Functions

    Directional impedance quadrilateral ZMCPDIS, Distance measuring zone, ZMCAPDIS quadrilateral characteristic for series compensated lines ZDSRDIR Directional impedance quadrilateral, including series compensation Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 34 Poleslip/out-of-step protection OOSPPAM Out-of-step protection ZCVPSOF Automatic switch onto fault 1-B35 1-B35 logic, voltage and current based ZGVPDIS Underimpedance 1-B14 1-B14 protection for generators and transformers Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 35: Back-Up Protection Functions

    VRPVOC Voltage restrained 1-C35 1-C35 1-C35 overcurrent protection APPTEF 67NT Average power transient 1-C54 1-C54 1-C54 earth fault protection Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 36 6-E01 frequency protection Multipurpose protection CVGAPC General current and 6-F02 6-F02 voltage protection General calculation SMAIHPAC Multipurpose filter 1) 67 requires voltage 2) 67N requires voltage Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 37: Control And Monitoring Functions

    DNP3.0 SINGLECMD Single command, 16 signals I103CMD Function commands for IEC 60870-5-103 I103GENCMD Function commands generic for IEC 60870-5-103 Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 38 RSMEMORY, SRMEMORY, TIMERSET, XOR ANDQT, Configurable logic blocks INDCOMBSPQT, Q/T (see Table INDEXTSPQT, INVALIDQT, INVERTERQT, ORQT, PULSETIMERQT RSMEMORYQT, SRMEMORYQT, TIMERSETQT, XORQT Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 39 REALSEL Analog input selctor for real values STOREINT Store value for integer inputs STOREREAL Store value for real inputs Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 40 Circuit breaker condition 0-18 monitoring LOLSPTR 26/49HS Transformer insulation 4-M21 4-M21 4-M21 loss of life monitoring I103MEAS Measurands for IEC 60870-5-103 Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 41 Table 3: Total number of instances for basic configurable logic blocks Basic configurable logic block Total number of instances GATE PULSETIMER RSMEMORY Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 42 RESIN1 RESIN2 POS_EVAL Evaluation of position indication XLNPROXY Proxy for signals from switching device via GOOSE GOOSEXLNRCV GOOSE function block to receive a switching device Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 43 Total number of instances for configurable logic blocks Q/T Configurable logic blocks Q/T Total number of instances ANDQT INDCOMBSPQT INDEXTSPQT INVALIDQT INVERTERQT ORQT PULSETIMERQT RSMEMORYQT SRMEMORYQT TIMERSETQT XORQT Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 44: Communication

    CHSEROPT DNP3.0 for TCP/IP and EIA-485 communication protocol MSTSER DNP3.0 serial master MST1TCP, MST2TCP, DNP3.0 for TCP/IP MST3TCP, MST4TCP communication protocol Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 45 DNP3 and IEC103 FSTACCSNA Field service tool access via SPA protocol over Ethernet communication FSTACCS Field service tool access Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 46 Binary signal transfer, 3/3/6 3/3/6 3/3/6 3/3/6 3/3/6 BinSignTrans1_2 transmit BinSignTransm2 BSR2M_305 Binary signal transfer, 2Mbit BSR2M_312 receive BSR2M_322 BSR2M_306 BSR2M_313 BSR2M_323 Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 47 Local acceleration logic 1-B35 1-B35 1-K01 1-K01 ECPSCH Scheme communication logic for residual overcurrent protection ECRWPSCH Current reversal and weak- end infeed logic for residual overcurrent protection Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 48: Basic Ied Functions

    Active parameter setting group TESTMODE Test mode functionality CHNGLCK Change lock function TERMINALID IED identifiers PRODINF Product information SYSTEMTIME System time LONGEN LON communication Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 49 General LED indication part for LHMI OPENCLOSE_LED LHMI LEDs for open and close keys GRP1_LED1– Basic part for CP HW LED indication module GRP1_LED15 GRP2_LED1– GRP2_LED15 GRP3_LED1– GRP3_LED15 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 51: Starting Up

    Check that the auxiliary supply voltage remains within the permissible input voltage range under all operating conditions. Check that the polarity is correct before energizing the IED. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 52: Energizing The Ied

    1 IED energized. Green LED instantly starts flashing 2 LCD lights up and "IED startup" is displayed 3 The main menu is displayed. A steady green light indicates a successful startup. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 53: Setting Up Communication Between Pcm600 And The Ied

    DHCP is available for the front port, and a device connected to it can thereby obtain an automatically assigned IP address via the local HMI path Main menu/ Configuration/ Communication/ Ethernet configuration/ Front port/ DHCP. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 54 Select Search programs and files in the Start menu in Windows. IEC13000057-1-en.vsd IEC13000057 V1 EN-US Figure 3: Select: Search programs and files Type View network connections and click on the View network connections icon. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 55 IEC13000059 V1 EN-US Figure 5: Right-click Local Area Connection and select Properties Select the TCP/IPv4 protocol from the list of configured components using this connection and click Properties. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 56 Use the ping command to verify connectivity with the IED. Close all open windows and start PCM600. The PC and IED must belong to the same subnetwork for this set-up to work. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 57: Writing An Application Configuration To The Ied

    IED when plotting the excitation characteristics. If the CT secondary circuit earth connection is removed without the current transformer primary being de-energized, dangerous voltages may result in the secondary CT circuits. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 58: Checking Vt Circuits

    Check that no short circuit jumpers are located in the slots dedicated for voltage. Trip and alarm circuits Check that the correct types of contacts are used. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 59: Checking The Binary Input/Output Circuits

    An IED equipped with optical connections has an minimum space requirement of 180 mm for plastic fiber cables and 275 mm for glass fiber cables. Check the allowed minimum bending radius from the optical cable manufacturer. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 61: Configuring The Ied And Changing Settings

    The primary CT data are entered via the HMI menu under Main menu /Configurations /Analog modules The following parameter shall be set for every current transformer connected to the IED: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 62: Supervision Of Input/Output Modules

    Each logical I/O module has an error flag that indicates signal or module failure. The error flag is also set when the physical I/O module of the correct type is not detected in the connected slot. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 63: Establishing Connection And Verifying The Spa/Iec Communication

    Verifying the communication M11735-77 v1 To verify that the rear communication with the SMS/SCS system is working, there are some different methods. Choose one of the following. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 64: Verifying Spa Communication

    (CCITT) characteristics. Table 12: Max distances between IEDs/nodes glass < 1000 m according to optical budget plastic < 25 m (inside cubicle) according to optical budget Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 65: Optical Budget Calculation For Serial Communication With Spa/Iec

    Losses in connection box, two contacts (1 dB/contact) 2 dB Margin for 2 repair splices (0.5 dB/splice) 1 dB Maximum total attenuation 11 dB 7 dB Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 67: Establishing Connection And Verifying The Lon Communication

    Glass fiber Plastic fiber Cable connector ST-connector snap-in connector Cable diameter 62.5/125 m 1 mm Max. cable length 1000 m 10 m Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 68: The Lon Protocol

    M11643-1 v4 LON communication setting parameters (Table 15) and LON node information parameters (Table 16) can only be set via the LON Network Tool (LNT). Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 69: Optical Budget Calculation For Serial Communication With Lon

    4 dB 0.3 dB/m plastic: 620 nm - 1mm 3 dB Margins for installation, aging, and so on 5 dB 2 dB Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 70 1.5 dB Losses in connection box, two contacts (1dB/contact) 2 dB Margin for repair splices (0.5 dB/splice) 0.5 dB Maximum total attenuation 11 dB 7 dB Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 71: Establishing Connection And Verifying The Iec 61850 Communication

    Ethernet ports. Verify that either signal status (depending on which connection that was removed) is shown as Error and the that other signal is shown as Ok. Be sure to re-connect the removed connection after completed verification. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 73: Establishing Connection And Verifying The Ieee C37.118/1344 Communication

    Front port is not available in the IED’s with blank front panel. By default, AP1 is available for engineering. To enable IEEE C37.118/1344 synchrophasor communication: Enable communication for by navigating to: Main menu /Configuration /Communication / Ethernet configuration . Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 74: Setting The Tcp/Udp Client Communication

    PMU Connection Tester tool The following steps explain how to set the PMU Connection Tester parameters in order to establish an IEEE C37.118 connection with the PMU: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 75 Alternatively, in order to make an IEEE1344 communication, the 1344TCPport parameter setting can be used (4713 is default). 2.3. Set the Protocol as IEEE C37.118.2-2011. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 76 TCPportUDPdataCtrl1 as one of the UDP communication parameters. 3.5. Save the Alternate Command Channel Configuration settings. 3.6. Continue to the section Verifying the IEEE C37.118/1344 UDP communication Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 77: Verifying The Communication

    Frequency, data Reporting Rate, Phasor names, and Phase angles of the reported synchrophasors. Observe the real-time frame details of the Data Frame in the bottom of the window. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 78 Open the drop-down menu in the Command field. There is a list of commands that can be sent from the client (PMU Connection Tester) to the PMU. Try different commands and make sure that the PMU is receiving and responding to them. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 79 HeaderFrame is not included, ask the PMU to send the header frame via the Send Header Frame command (Previous stage). Open each message type and observe the content of each message. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 80 File /Capture /Start Stream Debug Capture... The tool will ask to Set Stream Debug Capture File Name and path to save the capture file. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 81 Start capturing the IEEE C37.118 synchrophasor data • The synchrophasor data capturing process can be stopped at any point of time by navigating to File /Capture /Stop Stream Debug Capture... Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 82 (See figure 16), the capture process should start before connecting the PMU Connection Tester to the PMU, i.e. first start the capturing and then click Connect. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 83: Verifying The Ieee C37.118/1344 Udp Communication

    Now it should be possible to see the streaming synchrophasor data. • Verify the communication by following the same steps as in section Verifying the IEEE C37.118/1344 TCP communication. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 84: Optical Budget Calculation For Pmu - Pdc Communication

    Losses in the connectors and splices are typically 0.3dB/connection. The user must reserve 3dB spare for the uncertainty of the measurements. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 85: Testing Ied Operation

    A PC with PCM600 application configuration software in work online mode All setting groups that are used should be tested. This IED is designed for a maximum continuous current of four times the rated current. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 86: Preparing The Ied To Verify Settings

    For information about the functions to test, for example signal or parameter names, see the technical manual. The correct initiation of the disturbance recorder is made on start and/or release or trip from Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 87: Activating The Test Mode

    Use COMBITEST test system to prevent unwanted tripping when the handle is withdrawn, since latches on the handle secure it in the half withdrawn position. In this position, all voltages and Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 88: Connecting The Test Equipment To The Ied

    Release the tested function(s) by setting the corresponding Blocked parameter under Function test modes to No in the local HMI . Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 89: Verifying Analog Primary And Secondary Measurement

    Inject an unsymmetrical three-phase voltage and current, to verify that phases are correctly connected. If some setting deviates, check the analog input settings under Main menu /Configuration /Analog modules Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 90: Testing The Protection Functionality

    For outputs, any output relay can be forced to be active or not, regardless of the current requested state of the output in the IED logic configuration. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 91: How To Enable Forcing

    Forcing by using LHMI GUID-D885671F-79E5-4B75-8777-B59E44F6FCFC v1 Editing a signal value directly GUID-E0C115BE-3AD1-48C7-BA2D-29857CD3D3ED v1 • Edit the input/output value directly to select the desired logical level, by doing following: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 92 Set the status of a signal to Forced, in the forcing menu that corresponds to the I/O card in question. See example of LHMI menu in figure Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 93: Forcing By Using Pcm600

    Click Start editing signal value for forcing on the tool bar. IEC15000024 V1 EN-US The Signal Monitoring menu changes and indicates the forcing values that can be edited. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 94: How To Undo Forcing Changes And Return The Ied To Normal Operation

    Regardless of which input/output signals have been forced, all forced signals will return to their normal states immediately when the IED is taken out of test mode. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 95: Undo Forcing By Using Testmode Component

    LHMI. If the IED is left in test mode, then it is still possible to perform new forcing operations, both from LHMI and from PCM600 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 97: Testing Functionality By Secondary Injection

    Disturbance upload can be performed by the use of PCM600 or by any third party tool with IEC 61850 protocol. Reports can automatically be generated from PCM600. Disturbance files can be analyzed by any tool reading Comtrade formatted disturbance files. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 98: Event Recorder (Er) And Event List (El)

    EF4PTOC under Main menu /Test /Function test modes /Current protection is set to Off, since they are configured to the same current Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 99: Completing The Test

    11.3.2.1 Verifying the settings SEMOD55257-46 v5 Connect a single-phase or three-phase test set to inject the operating voltage. The injection is done across the measuring branch. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 100: Completing The Test

    2.2.3 2.2.3 2.2.4 2.2.4 The upper limit of ROA setting range is changed from 90 degrees to 119 degrees. 2.2.5 11.3.3.2 Verifying the settings SEMOD55252-86 v12 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 101: Completing The Test

    Reduce the injected voltage stepwise to 90 % of the operate level, and check the time delay. Repeat points 3– 6 for phases L2 and L3. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 102: Completing The Test

    All other protection functions, which may interfere with testing or tripping shall have the setting Blocked set to Yes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 103: Verifying The Zero-Sequence Current Reduction From The Winding One Side

    Easy and Intuitive Method for Testing Transformer Differential Relays published by Hitachi Power grids. This paper is available on the Hitachi Power grids website. To prepare the function to be tested for specific phase angle shift (e.g. specific tap position) of the protected PST, proceed as follows: Make sure that the binary input STOPCOMP into PSTPDIF function has the logical value zero.
  • Page 104: Verifying The Three-Phase Pickup From Winding One Side

    Equal to the tested three-phase pickup value from winding one side if the parameter ZSCurrSubtrW1 = Off. • Greater for factor 1.5 from the tested three-phase pickup value from winding one side if the parameter ZSCurrSubtrW1 = On. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 105: Verifying The Zero-Sequence Current Reduction From Winding Two Side

    The operating secondary current should have the following value: CTsec  IdMin I P ickup Base W Ph W CTprim (Equation 4) IECEQUATION18060 V1 EN-US Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 106: Verifying The Single-Phase Pickup From Winding Two Side

    • When ZSCurrSubtrW2 = On, this factor will have a value between 1.50 and 1.732 depending on the actual phase angle shift as shown in Figure Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 107: Verifying The Operate Characteristic

    Easy and Intuitive Method for Testing Transformer Differential Relays published by Hitachi Power grids. When correct currents are injected, check that all three differential currents are approximately 0% and the bias current is equal to x*100%.
  • Page 108: Completing The Test

    When the load current compensation is inactive, the dotted lines and test point 13 are valid. Test points 5, 6, and 7 are not valid for this measurement. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 109 Exact –0.5 x R1 x tan(ArgNegRes=30°) –0.23 x X1 0.8 x X1 Exact –0.5 x R1 x tan(ArgNegRes=30°) –0.37 x X1 Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 110 RFPE 0.85 x RFPE x tan(ArgLdset) ArgLd = angle for the maximal load transfer 0.85 x RFPE RLdFwset x tan(ArgLdSet) RLdFw Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 111: Measuring The Operating Limit Of Set Values

    21. Compare the result of the measurement with the setting t1PE. Repeat steps 1 to 3 to find the operating time for all other used measuring zones. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 112: Completing The Test

    60° ArgNegRes loop 50% of RLdFw RFFwPE IEC09000734-4-en.vsd IEC09000734 V4 EN-US Figure 27: Operating characteristic for phase selection function, forward direction single- phase faults Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 113 ArgLd ArgNegRes 60° phase ArgDir 50% RLdFw 0.5·RFFwPP IEC09000735-3-en.vsd IEC09000735 V3 EN-US Figure 28: Operating characteristic for phase selection function, forward direction phase-to- phase faults Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 114: Measuring The Operating Limit Of Set Values

    Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". Consider releasing of the zone to be tested by setting the phase selector FMPSPDIS to On. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 115: Phase-To-Phase Faults

    After the timer tPP for the actual zone has elapsed, also the signals TRIP, TRPP and TRx shall be activated. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 116: Phase-To-Earth Faults

    Measure operating characteristics during constant current conditions. Keep the measured current as close as possible to its rated value or lower. But make sure it is higher than 30% of the rated current. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 117 50% of RFPPZx/2 RFPPZx/2 IEC05000368-5-en.vsdx IEC05000368 V5 EN-US Figure 31: Distance protection characteristic with test points for phase-to-phase measurements Table is used in conjunction with figure 31. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 118 0.8 x RFPP/2 –0.4 x RLdFw x tan(ArgDir) 0.4 x RLdFw 0.5 x X1 Exact –0.5 x R1 x tan(ArgNegRes-90) –0.23 x X1 Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 119: Measuring The Operating Limit Of Set Values

    0.5 x (2 x X1 + X0 0.5 x (2 x R1 + R0 RFPE 11.4.5.1 Measuring the operating limit of set values GUID-02EE80DB-CE52-49F0-99C4-14FD84766009 v3 Procedure: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 120: Measuring The Operating Time Of Distance Protection Zones

    To verify the settings the operating points according to figures should be tested. See also tables for information. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 121 ArgLd ArgNegRes 60° phase ArgDir 50% RLdFw 0.5·RFFwPP IEC09000735-3-en.vsd IEC09000735 V3 EN-US Figure 34: Operating characteristic for phase selection function, forward direction phase-to- phase faults Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 122: Measuring The Operating Limit Of Set Values

    28. The corresponding binary signals that inform about the operation of the phase selection measuring elements are available in the local HMI under Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 123: Completing The Test

    Load compensation and direction element are improved for earth faults without zero sequence current condition. This update is valid for all the previously released 2.2 products. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 124: Verifying The Settings

    Distance protection characteristic with test points for phase-to-phase measurements Table 30: Test points for phase-to-phase loops L1-L2 (Ohm/phase) Test point Reach Set value Comments Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 125 25% of RFPEZx 50% of RFPEZx alt. 80% of RFPEZx RFPEZx (Load encroachment) IEC05000369-5-en.vsdx IEC05000369 V5 EN-US Figure 36: Distance protection characteristic with test points for phase-to-earth measurements Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 126: Measuring The Operating Limit Of Set Values

    Observe that the zones that are not tested have to be blocked and the zone that is tested has to be released. Repeat steps to find the operating value for the phase-to-earth fault L3-E according to figure and table . Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 127: Measuring The Operating Time Of Distance Protection Zones

    Load compensation and direction element are improved for earth faults without zero sequence current condition. This update is valid for all the previously released 2.2 products. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 128: Verifying The Settings

    X1set R (Ohm/phase) ArgDir 25% of RFPPZx/2 50% of RFPPZx/2 RFPPZx/2 IEC05000368-5-en.vsdx IEC05000368 V5 EN-US Figure 37: Distance protection characteristic with test points for phase-to-phase measurements Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 129 Exact –0.5 x R1 x tan(ArgNegRes=30°) –0.37 x X1 0.5 x X1 0.5 x R1 0.5 x RFPPZx Table is used in conjunction with figure . Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 130 –02143 x RLdFw Exact: 0.8 x RFPEZx x tan (ArgDir=20°) 0.8 x RLdFw –0.8 x RLdFw x tan(ArgDir=20°) 0.8 x RLdFw Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 131: Measuring The Operating Limit Of Set Values

    This essentially means that the test equipment has to be able to generate currents with a DC-component Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 132: Completing The Test

    Test of the interactions or combinations that are not configured are not considered in this instruction. Always set Operation to On to check the performance of power swing detection, blocking and unblocking during testing. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 133 ΔRv = RLdOutRv – (kLdRRv *RLdOutRv) RLdInFw = kLdRFw * RLdOutFw RLdInRv = kLdRFw * RLdOutFw X1OutFw = X1InFw + ΔFw X1OutRv = X1InRv + ΔRv Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 134 -(0.8 * -R1FInRv + ∆Rv) * tan (ArgLd) -RLdInRv -R1FInRv If OperationLdCh = Off -0.8 * R1FInRv (0.8 * -R1FInRv + ∆Rv) * tan (ArgLd) -R1FInRv 0.8 * X1InFw Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 135 Inject voltage in one of the three phases in accordance with the test point P1 by keeping constant current in three phases throughout testing and maintaining rated voltage for the other two phases. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 136 Create a condition such that residual current is measured (that is, earth fault occurs in the power system) and its value should be above the value seen during unbalanced loading Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 137 Testing the power swing unblocking logic GUID-1B635221-493D-4DB3-938C-6C61461E3B16 v1 Preconditions The following output signals shall be configured to binary outputs: FLTL1, FLTL2, FLTL3, FLT1PH, FLT2PH, FLT3PH and START. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 138: Completing The Test

    IED. If not, configure connections to unused binary outputs, for test purposes. 11.4.10.1 Function revision history GUID-DFB27CD5-5AC0-4D8B-B306-F74173F71E4E v1 Document Product History revision revision 2.2.1 2.2.1 2.2.2 Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 139: Testing The Carrier Send And Trip Signals

    Switch the operation of the zone 1 distance protection function on and fulfill all the conditions for single-pole autoreclosing. Simulate a single phase-to-earth fault within the reach of zone 1 and both power-swing zones. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 140: Checking The Underreaching Zone

    (IBase). The angle between the voltage and current shall be 0°. With maintained amplitude of the injected voltage the current amplitude and angle is changed to a value ZC/2. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 141 0.92 UBase the START signal should be activated. In addition to this the signal ZONE2 should be activated. Set N2Limit to 1 and repeat step 6. Now the signals TRIP2 and TRIP should be activated. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 142 Zone 2 X’ Pole slip impedance movement Zone 2 TripAngle Zone 1 WarnAngle IEC07000099_2_en.vsd IEC07000099 V2 EN-US Figure 41: Setting of the pole slip protection PSPPPAM Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 143: Completing The Test

    The protection function performs a simple summation of the currents of the two channels I3P1 and I3P2. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 144: Verifying The Settings

    SE and RE. 2 5 8367 20918 × × Base (Equation 7) EQUATION14043 V1 EN-US Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 145 EQUATION14052 V1 EN-US 0 003 0 282 20918 0 282 2 20918 5899 × × × × t RvsZ RvsZ RvsR RvsX (Equation 17) EQUATION14053 V1 EN-US Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 146 49.5 Hz for the test as generator in the quadrant 1 and 2 of the R-X plane • 50.5 Hz for the test as generator in the quadrant 3 and 4 of the R-X plane Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 147: Test Of Point Re (R Fwdr , X Fwdx )

     = arctan arctan 82. . 14°       ForwardR 8 19 (Equation 22) EQUATION14058 V1 EN-US frequency of V = 50 Hz Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 148 59 33 ∠  =  = arctan arctan 82. . 14°       ForwardR 8 19 (Equation 28) EQUATION14058 V1 EN-US Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 149 Check that the service values (VOLTAGE, CURRENT, R(%), X(%) ) are according to the injected quantities and that ROTORANG is close to 3.14 rad. For this particular injection the service values are: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 150 ∠I = 180º frequency of I = 49.5 Hz Expected result: start of the protection function and trip in zone 2, when trip conditions are fulfilled. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 151: Test Of The Boundary Between Zone 1 And Zone 2, Which Is Defined By The

    Steady voltage and current are applied in order to get a steady high impedance, that is a point in the plane R-X that is far away from the lens characteristic. Define the following three-phase symmetrical quantities (the phase angle is related to phase L1): Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 152 Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 0 9 1435 9 36 × × × × t RZ 13 8 VT p (Equation 51) EQUATION14066 V1 EN-US Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 153 = 0 A = 0 A • State 2: main test step. Define the following three-phase symmetrical quantities (the phase angle is related to phase L1): Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 154: Test Of The Point Se (R Rvsr , X Rvsx )

    V = 50 Hz 10459 1 162 × × 9000 (Equation 63) EQUATION14059 V1 EN-US ∠I = 0º frequency of I = 50 Hz Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 155 0.29 (Equation 68) EQUATION14068 V1 EN-US frequency of V = 50 Hz 10459 1 162 × × 9000 (Equation 69) EQUATION14059 V1 EN-US ∠I = 0º Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 156 Execution of the dynamic test GUID-31EF4F76-8FC8-4952-896C-B3A8A5FD635A v1 The test may be performed by using two states of a sequence tool that is a basic feature of test sets. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 157 Expected result: the protection function does not issue either start or trip. GUID-7C9F1163-0186-41DA-9D5F-DDA589323B9F v1 After each test it is possible to download and study the related disturbance recording. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 158: Automatic Switch Onto Fault Logic Zcvpsof

    Function revision history GUID-A7F84AD6-F164-491B-B25E-D3BB002E1BDA v3 Document Product History revision revision 2.2.1 2.2.1 2.2.2 2.2.3 2.2.3 2.2.4 2.2.4 Updated technical data for setting parameters tDuration, tDLD and tOperate. 2.2.5 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 159: Activating Zcvpsof Externally

    Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.4.14.1 Function revision history GUID-E2FF644E-DD3A-4549-B15A-2395B9709DA6 v2 Document Product History revision revision 2.2.1 2.2.1 2.2.2 Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 160: Verifying The Signals And Settings

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 161: Phase Preference Logic Ppl2Phiz

    No Trip 132a Trip No Trip No Trip Trip Trip No Trip 213a No Trip Trip Trip No Trip Trip No Trip Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 162: Completing The Test

    To verify the zone 1 mho characteristic, at least two points must be tested. Z1Fwd LineAngle Z1Rev IEC11000312-2-en.vsd IEC11000312 V2 EN-US Figure 45: Proposed four test points for phase-to-phase fault Where, Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 163 (where x is 2- 3 depending on the zone selected) LineAngle is the Impedance angle for phase-to-phase fault in degrees Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 164: Completing The Test

    ZGVPDIS /1: ZGVPDIS for the function, or for each individual function in a chain, to be tested next. Remember to set the parameter Blocked to Yes, for each individual function that has been tested. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 165: Current Protection

    Function status/Current protection/PhaseOverCurrent4Step(51_67,4(3I>)) / OC4PTOC(51_67;4(3I>)):x, where x = instance number. The Signal Monitoring in PCM600 shows the same signals that are available on the local HMI. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 166: Function Revision History

    3.2. Increase the injected current, note the operate value of the tested step of the function and compare it to the set value. 3.3. Decrease the current slowly, note the reset value and compare it to the reset ratio 95%. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 167: Completing The Test

    Switch the fault current off. Do not exceed the maximum permitted overloading of the current circuits in the IED. Compare the measured operating current with the set value. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 168: Completing The Test

    L2 and L3 with a polarizing voltage connected to terminals L2, respectively L3. Block lower set steps when testing higher set steps according to the instructions that follow. Connect a trip output contact to a timer. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 169: Four Step Non-Directional Earth Fault Protection

    Inject pure negative sequence current, that is, phase currents with exactly same magnitude, reversed sequence and exactly 120° phase displaced into the IED with an initial value below Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 170: Completing The Test

    Sensitive directional residual overcurrent and power protection SDEPSDE SEMOD175060-3 v7 Prepare the IED for verification of settings as outlined in section "Requirements" section "Preparing for test" in this chapter. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 171: Measuring The Operate And Time Limit For Set Values

    1.2 · UNRel>. × kSN Sref Tinv × × test test (Equation 81) IECEQUATION2402 V2 EN-US Compare the result with the expected value. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 172 Continue to test another function or complete the test by setting the test mode to Off. RCADir Operate area 3 × ROADir IEC06000650_2_en.vsd IEC06000650 V2 EN-US Figure 48: Characteristic with ROADir restriction Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 173 The expected value depends on whether definite or inverse time was selected. Continue to test another function or complete the test by setting the test mode to Off. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 174 The expected value depends on whether definite time tINNonDir or inverse time was selected. Continue to test another function or complete the test by setting the test mode to Off. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 175: Completing The Test

    Monitor the signal START until it disappears on the corresponding binary output or on the local HMI, take the TEMP readings and compare with the setting of ReclTemp. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 176: Completing The Test

    IBase1. Finally check that start and trip information is stored in the event menu. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 177: Completing The Test

    Compare the result with the set IP>. If RetripMode = Off and FunctionMode = Current is set, only backup trip can be used to check set IP>. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 178: Checking The Residual (Earth Fault) Current Operate Value In> Set Below Ip

    Apply the fault condition, including start of CCRBRF, with current below set current value. Verify that re-trip is achieved after set time t1, but no back-up trip is obtained. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 179: Verifying The Back-Up Trip Mode

    11.5.9.8 Verifying the case FunctionMode = CB Pos GUID-06D1545D-31F7-4B48-821E-151212962A81 v1 It is assumed that re-trip without current check is selected, RetripMode = UseFunctionMode. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 180: Verifying The Case Retripmode = Contact

    Arrange disconnection of CB closed signal(s) well before set back-up trip time t2. It simulates a correct CB tripping. Verify that back-up trip is not achieved. Re-trip can appear for example, due to selection RetripMode = Always. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 181: Verifying The External Start Signal Has Timed Out

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 182: Stub Protection Stbptoc

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 183: Overcurrent Protection With Binary Release Brptoc

    No STL1, START, and TRIP signal should appear. Switch the fault current off. Repeat the above steps by injecting fault current in phase L2 and L3. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 184: Completing The Test

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 185: Directional Underpower Protection Guppdup

    L1L2 × (Equation 87) EQUATION1700 V1 EN-US L2L3 × (Equation 88) EQUATION1701 V1 EN-US L3L1 × (Equation 89) EQUATION1702 V1 EN-US Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 186: Completing The Test

    Angle1, angle for stage 1 (equal to 0° for low forward power protection and equal to 180° for reverse power protection). Check that the Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 187: Completing The Test

    Activate the BLOCK binary input. Switch on the fault current (110% of the setting) and wait longer than the set value tOper. No TRIP signal should appear. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 188: Completing The Test

    Therefore it is best to switch them off during this test. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 189 Check that service value from the function for current in phase L1, on the local HMI under Main menu /Test is approximately 382A (that is, 0.763A · (500/1) = 382A). Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 190 Check that service value for current in phase L1, on the local HMI under Main menu /Test is approximately 411A (that is, 0.822A · (500/1) = 411A). Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 191: Completing The Test

    11.5.17.1 Verifying settings by secondary injection GUID-EB788169-532A-4A3E-BBEC-DCB28169DF86 v7 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 192 Ampl = 1.1 A Angl = 15 deg Ampl = 0.6 A Angl = 97 deg Ampl = 1.3 A Angl = -135 deg Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 193: Completing The Test

    The set operate value in secondary amperes is calculated according to the following equations: First part of the characteristic (Restrain voltage ≤ 25% of UBase): Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 194 IL1 from 0.0 A up to the value the function operates. The START and STOC signals must be activated when the amplitude of the phase current IL1 is slightly above 0.25 A Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 195 Note the operate value. The set operate value in secondary volts is calculated according to the following equation: StartVolt UBase × × VTprim (Equation 99) IECEQUATION2436 V1 EN-US Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 196: Completing The Test

    Injected quantities provided below are only for the neutral current IN and the neutral voltage UN. This assumes that these two quantities are connected to the IED on separate inputs and connected to the Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 197 1) Inject set value for IMinForward –1.5% of CT secondary rated current, ( 0.025A-0.015A when IMinForward =2.5% and CT rated secondary is 1A)). The following signal is given from the APPTEF function: • Only STUN at the beginning of injection. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 198 Inject the following analogue quantities given in secondary amperes and volts and wait for three seconds in order to obtain the trip output (default delay for tTrip=2s): Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 199: Completing The Test

    Continue to test another function or end the test by navigating to Main menu/Test/IED test mode/ TESTMODE: 1 and change the IEDTestMode setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 200: Voltage Protection

    IECEQUATION2428 V1 EN-US where: t(s) Operate time in seconds Settable time multiplier of the function for step 1 Measured voltage U1< Set start voltage for step 1 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 201: Completing The Test

    Repeat the above described steps for Step 2 of the function. 11.6.2.2 Extended testing GUID-BE4B4A36-CCEE-4020-B7DC-6A83A43D11F5 v2 The tests above can be repeated for 2 out of 3 and for 3 out of 3 operation mode. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 202: Completing The Test

    Settable time multiplier of the function for step 1 Measured voltage U1> Set start voltage for step 1 Repeat the test for Step 2 of the function. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 203: Completing The Test

    Voltage differential protection VDCPTOV SEMOD175258-3 v2 Prepare the IED for verification of settings as outlined in section "Requirements" and section "Preparing for test" in this chapter. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 204: Function Revision History

    Apply voltage higher than the highest set value of UDTrip, U1Low and U2Low to the U1 three- phase inputs and to one phase of the U2 inputs according to figure 51. The voltage differential START signal is set. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 205 The connections to U1 must be shifted to test another phase. (UL1 to UL2, UL2 to UL3, UL3 to UL1) Check of U2Low SEMOD175258-91 v3 Procedure Connect voltages to the IED according to valid connection diagram and figure 52. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 206: Check Of Voltage Differential Trip And Alarm Levels

    U2Low. 11.6.5.3 Check of voltage differential trip and alarm levels SEMOD175258-104 v3 Procedure Connect voltages to the IED according to valid connection diagram and figure 53. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 207: Check Of Trip And Trip Reset Timers

    Increase the voltage until START signal resets. Measure the time from reset of START signal to reset of TRIP signal. Check the measured time by comparing it to the set trip reset time tReset. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 208: Final Adjustment Of Compensation For Vt Ratio Differences

    Inject the measured voltages at rated values for at least set tRestore time. Activate the BLOCK binary input. Simultaneously disconnect all the three-phase voltages from the IED. No TRIP signal should appear. Reset the BLOCK binary input. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 209: Completing The Test

    Values of the logical signals and the service values for SCCFPVOC are available on the local HMI under: Main menu/Tests/Function status/Unbalance protection/ CapBankCascadingFail(51V,2(I>/U<))/SCCFPVOC (51V, 2(I>/U<)):x, where x = instance number. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 210 Values of the logical signals and service values for SCCFPVOC are available on the local HMI under: Main menu/Tests/Function status/Unbalance protection/ CapBankCascadingFail(51V,2(I>/U<))/SCCFPVOC (51V, 2(I>/U<)):x, where x = instance number. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 211: Completing The Test

    Ensure that mandatory three-phase currents and unbalance currents are connected to the separate SMAI blocks and their outputs are connected to the I3P and I3UNB inputs of the SCUCPTOC function. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 212 IUNBCLCL1 = 1.5 A which is equivalent to 15% of Change I = 0.35∠0° A UNBL1UNBˍA IBase2 ALARM TEST Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 213 The logical signals and service values for SCUCPTOC function are available on the local HMI under: Main menu/Tests/Function status/Unbalance protection / CapBankCurrentUnbalance(60N, Iub>)/SCUCPTOC(60N, Iub>):x/outputs , where x = instance number. To store the unbalance current values, perform these steps: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 214 = 0.45∠0° A, IUNBCLCL1, IUNBCLCL2, and IUNBCLCL3 should show 2.5 A which is equivalent to 25% of IBase2 START and TRIP TEST Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 215: Completing The Test

    Grounded - Select this option by using the parameter setting SCBGndType, if the capacitor bank is grounded. • Ungrounded - Select this option by using the parameter setting SCBGndType, if the capacitor bank is ungrounded. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 216 = 24.25 V in secondary at rated • DIFURATL1 should TapL1 become HIGH frequency • URATIOL1 and USEDURATL1 should show 0.382 and 0.5 respectively Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 217 To calculate PUDIFL1 in steps 4-f, 4-g and 4-h, use the following equations:    UDIFL TapL USEDURATL (Equation 110) IECEQUATION19217 V1 EN-US Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 218 LASTCOMP output should display the date and time of compensation • URATIOL1 and USEDURATL1 should show 0.406 • DIFURATL1 should become Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 219 Operation =ON • tDefWrn =5 s; tDefAlm =5 s; tDefTrip =5 s • SCBGndType =Ungrounded • NeutVoltMeas =Not available • Udif> =10% UB • UdifAlm> =8% UB Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 220 HIGH after a time delay given by frequency the setting tDefAlm • PUDIFL1 should show 8.06% TRIP Signal Test Repeat Sub-step 4–a Sub-step 4–b Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 221: Completing The Test

    Set the following parameters: • Operation = ON • tDefTrip = 5.00 s; tDefAlm = 5.00 s; tDefWrn = 5.00 s • UNUnbal> = 5.5% UBase Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 222 The voltage inputs U , and U refer to the bus voltages and U refers to the neutral voltage input. Check the respective operation of warning, alarm, and trip. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 223: Completing The Test

    Note the frequency value at which the START signal appears and compare it with the set value StartFrequency. Increase the frequency until its rated value is reached. Check that the START signal resets. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 224: Completing The Test

    (80 - 90 ms). Extended testing M16290-28 v4 The test above can be repeated to check the time to reset. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 225: Completing The Test

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 226: Multipurpose Protection

    CurrentInput) is created from the test set. Increase the current(s) until the low set stage operates and check against the set operate value. Decrease the current slowly and check the reset value. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 227: Overcurrent Feature With Current Restraint

    DirPrinc_OC2 set to I · cos(F). This has to be known if a more detailed measurement of the directional characteristic is made, than the one described below. Procedure Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 228: Over/Undervoltage Feature

    Inject a current 0.1 · IBase to the reference current input I5. Increase slowly the current in one of the phases and check that FAIL output is obtained when the current is above 0.9 · IBase. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 229: Completing The Test

    Slowly decrease the measured voltage in one phase until the BLKU signal appears. Record the measured voltage and calculate the corresponding negative-sequence voltage according to the equation (observe that the voltages in the equation are phasors): Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 230: Measuring The Operate Value For The Zero-Sequence Function

    IEC00000275 V1 EN-US Compare the result with the set value of the zero-sequence operating voltage (consider that the set value 3U0> is in percentage of the base voltage.) Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 231: Measuring The Operate Value For The Dead Line Detection Function

    Connect the nominal voltages in all three phases and feed a current below the operate level in all three phases. Keep the current constant. Disconnect the voltage in all three phases simultaneously. The BLKU, BLKZ and 3PH signals should not appear. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 232: Completing The Test

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 233: Voltage Based Delta Supervision Delvspvc

    11.10.5 Current based delta supervision DELISPVC GUID-9EAEFF02-62C2-4FA7-8F3D-E92391206F7F v2 Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 234: Verifying The Signals And Settings

    Make sure that the function is connected to any of the available real derived outputs, for example the P output signal of the CMMXU function. Set the following parameters: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 235: Completing The Test

    Figure shows the general test connection for a 1½ breaker diameter with one-phase voltage connected to the line side. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 236: Testing The Synchronizing Function

    General test connection for a 1½ breaker diameter with one-phase voltage connected to the line side 11.11.1.1 Testing the synchronizing function M2377-21 v8 The voltage inputs used are: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 237: Testing The Synchrocheck Functionality

    The settings used in the test shall be final settings. The test shall be adapted to site setting values instead of values in the example below. Test with no voltage difference between the inputs. Test with a voltage difference higher than the set UDiffSC. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 238 FreqDiffA and FreqDiffM respectively and that operation is blocked when the frequency difference is greater. Test with frequency difference = 0 mHz Test with a frequency difference outside the set limits for manual and auto synchronizing check respectively. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 239: Testing The Energizing Check

    The test should verify that the energizing check function operates for a low voltage on the U-Bus and for a high voltage on the U-Line. This corresponds to an energizing of a dead bus to a live line. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 240: Testing The Voltage Selection

    One-and-a-half breaker arrangement. Apply a single-phase voltage of 100% GblBaseSelLine to the U-Line and a single-phase voltage of 100% GblBaseSelBus to the U-Bus. Verify that correct output signals are generated. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 241 1 ½ bus alt. WA2 – LINE2_QB B2SEL, (Operates on LINE2 LN2SEL WA2_QA1) (mirrored) WA2 – TIE_QA1 LINE1_QB B2SEL, LINE1 LN1SEL WA2 – TIE_QA1 WA1_QA1 B1SEL, B2SEL Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 242: Completing The Test

    (CB) is simulated by an external bi-stable relay (BR), for example a relay type RXMVB2 or RXMD or Breaker Simulator of Hitachi Power grids. The following manual switches are used: Transformer protection RET670 Commissioning manual ©...
  • Page 243 Two push-buttons (SC, ST) to operate the BR and a change-over switch (SRY) to simulate CBREADY • Possibly a switch simulation the synchronizing check SESRSYN condition Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 244: Preparation Of The Verification

    If external control inputs OFF/ON are used, check that they work. Set ExternalCtrl = On and use the control inputs to switch On and Off, and check the state of the function. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 245: Verifying The Auto Recloser

    INHIBIT. Check that the auto reclosing sequence is interrupted and no auto reclosing takes place. Check closing onto a fault M12400-137 v5 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 246 Restoring equipment M12400-190 v6 After the tests, restore the equipment to normal or desired state. Check the following items in particular: Check the operation counters. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 247: Completing The Test

    Setting confirmation is an important step for voltage control in the installation and commissioning phase to ensure consistency of power systems base quantities, alarm/blocking conditions and parallel control settings for each transformer control function. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 248 TR1ATCC(90, U↕):x/TR8ATCC(90, U↕||):x /Time /t1 and t2 For cases where single-mode voltage control is implemented, the Parameter Setting menu structure includes TR1ATCC:1 instead of the parallel designator TR8ATCC:1. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 249: Secondary Test

    Review the expected time for first (t1) and subsequent (t2) tap change commands from the voltage control function on the local HMI under Main menu /Settings /IED Settings /Control / Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 250: Check The Undervoltage Block Function

    Confirm the voltage control function response to an applied current above Iblock, by reviewing the settings in the local HMI under Main menu /Settings /IED Settings /Control / TransformerVoltageControl(90, U↕) /TR1ATCC(90, U↕):x/TR8ATCC(90, U↕||):x /OVPartBk. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 251: Single Transformer

    Confirm on the local HMI that service values for bus voltage and load current are equal to injected quantities. Confirm that the calculated value for load voltage, displayed on the local HMI, is equal to that derived through hand calculations. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 252: Parallel Voltage Regulation

    Setting confirmation through secondary injection requires calculation of circulating currents for each transformer based on impedance values and respective compensating factors, and is therefore more complex for greater than two transformers. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 253 U so that Ui is outside the voltage deadband created by setting UDeadband. Expressed by equation and equation 128. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 254 TR8ATCC responds in accordance with the setting for CircCurrBk. Alarm and blocking conditions can be confirmed through interrogation of the event menu or the control menu on the local HMI. VTmismatch during parallel operation SEMOD175185-859 v4 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 255: Completing The Test

    Activation of the different zones verifies that the CS signal is issued from the intended zones. The CS signal from the independent tripping zone must have a tSendMin minimum time. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 256: Function Revision History

    Check that trip time complies with the zone timers and that correct trip outputs, external signals, and indications are obtained for the actual type of fault generated. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 257: Testing Blocking Scheme

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 258: Phase Segregated Scheme Communication Logic For Distance Or Overcurrent Protection Zpcpsch

    Activate the receive (CRLx) signal in the IED. Apply healthy normal load conditions to the IED for at least two seconds. Apply a fault condition within the permissive zone. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 259: Testing Blocking Scheme

    The current reversal logic and the weak-end infeed functions are tested during the secondary- injection test of the impedance or overcurrent protection zones together with the scheme communication logic for the distance protection function ZCPSCH. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 260: Function Revision History

    Restore the forward and reverse zone timer to its original setting. 11.12.3.3 Weak end infeed logic M14947-37 v2 Weak-end infeed logic at permissive overreach schemes M14947-39 v5 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 261: Completing The Test

    The current reversal and weak-end-infeed functions shall be tested together with the permissive scheme. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 262: Function Revision History

    No TRIP signal should appear. Switch the fault current and the polarizing voltage off. Reset the BLOCK digital input. Permissive scheme M13926-42 v8 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 263: Completing The Test

    Inject current (180° — AngleRCA) in one phase to about 110% of the set operating current of the four step residual overcurrent protection (IN>Dir). Check that the IRVL output is activated in the disturbance recorder after the set time tPickUpRev. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 264: Testing The Weak-End Infeed Logic

    Reset the CRL binary input. Activate the BLOCK binary input. Activate the CRL binary input. No ECHO, CS and TRWEI outputs should appear. Reset the CRL and BLOCK binary input. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 265: Completing The Test

    TRIN. IEC 61850 mapping is made for the added output. The block logic is corrected for the lockout functionality. 2.2.5 11.13.1.2 3 phase operating mode SEMOD54375-106 v10 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 266: 1Ph/3Ph Operating Mode

    1ph/2ph/3ph operating mode SEMOD54375-143 v6 In addition to other tests, the following tests, which depend on the complete configuration of an IED, should be carried out. Procedure Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 267: Circuit Breaker Lockout

    Besides the TRIP outputs, CLLKOUT should be set. Reset the lockout signal by activating the reset lockout (RSTLKOUT) signal. Activate the trip signal lockout function, set TripLockout = On and repeat. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 268: Completing The Test

    If sensor quality is low, then lockout and alarm signals will get reset. 2.2.5 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 269: Testing The Gas Medium Supervision For Pressure Alarm And Pressure Lockout Conditions

    Check that the input logical signal BLOCK is logical zero and that on the local HMI, the logical signals LVLALM, LVLLO, TEMPALM, TEMPLO, ALARM and LOCKOUT are logical zero. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 270: Function Revision History

    Reset the BLOCK binary input. Ensure that temperature lockout condition exists and then activate the reset lockout input RESETLO and check that the outputs TEMPLO and LOCKOUT reset. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 271: Completing The Test

    Check that the output CBLIFEPH is decreased with a value that corresponds to the injected current. 6.4. CBLIFEAL is activated as soon as CBLIFEPH is below the set CBLifeAlmLevel value. Test of accumulated energy Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 272: Completing The Test

    The Limit counter function L4UFCNT can be tested by connecting a binary input to the counter and applying pulses to the counter. The speed of the pulses must not exceed the cycle time of the Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 273: Completing The Test

    ALARM2 signal appears. Note the time taken for the appearance of ALARM2 signal from the appearance of WARNING2 signal, and compare it with set value (tDelayToAlarm2). Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 274: Completing The Test

    Slowly increase any phase current of any winding to the threshold limit and wait until the ALARM signal appears. Compare the wait time with the set tMin value. Bring the injected three-phase currents to the rated value. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 275: Completing The Test

    Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.14.9.1 Verifying the signals and settings GUID-026F1A4F-E9A8-43DC-87E1-0831E0123E50 v1 The current can be injected using common test equipment. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 276: Completing The Test

    2.2.3 2.2.3 2.2.4 2.2.4 2.2.4 2.2.5 Updated monitoring till 9 order voltage harmonics. Refer to document revision H for monitoring till 5 order voltage harmonics. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 277: Voltage Harmonic Monitoring Vhmmhai

    11.14.12 Function revision history GUID-0AA99E78-0C76-48B5-AA00-8E3201C0D263 v1 Document Product History revision revision 2.2.1 2.2.1 2.2.2 2.2.3 2.2.3 2.2.4 2.2.4 2.2.5 New function release Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 278: Fault Current And Voltage Monitoring Function Fltmmxu

    GUID-1740AA05-417C-4474-ABE7-F15CB4D16019 v3 Document Product History revision revision 2.2.1 2.2.1 2.2.2 2.2.3 2.2.3 2.2.4 2.2.4 Added FLINVAL, FLT_DIST, FLT_R, and FLT_LOOP outputs in the ACT function block. 2.2.5 Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 279: Verifying The Signals And Settings

    EQUATION123 V1 EN-US in % for two- and three-phase faults × × + × X0 2 X1 (Equation 132) EQUATION124 V1 EN-US in % for single-phase-to-earth faults Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 280: Completing The Test

    Activate the STARTACC input and supply the IED with three-phase currents and voltages at their rated value. Check that the ACCINPRG signal appears continuously. Note the EAFACC and ERFACCvalue after 1 minute and compare it with calculated energy value. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 281: Completing The Test

    SEMOD53595-1 v1 11.16.1 Multiple command and transmit MULTICMDRCV / MULTICMDSND SEMOD172432-5 v3 The multiple command and transmit function (MULTICMDRCV / MULTICMDSND) is only applicable for horizontal communication. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 282: Remote Communication

    (BO). Check at End2 that the BI signal is received and the BO operates. Repeat the test for all the signals configured to be transmitted over the communication link. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 283: Basic Ied Functions

    Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to the original values, if changed for testing purposes. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 284: Exit Test Mode

    Navigate to the test mode folder. Change the On setting to Off. Press the 'E' key and the left arrow key. Answer YES, press the 'E' key and exit the menus. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 285: Primary Injection Testing

    If the function LDC is set to Zero, this test is omitted. Open the voltage control display on the LHMI in Main Menu /Control /Commands / TransformerVoltageControl (ATCC, 90) . Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 286: Voltage Control Of Parallel Transformers

    For parallel operation, it is also recommended to confirm the setting for the general parallel arrangement of transformers in Main menu /Settings/IED Settings /Control/ TransformerVoltageControl(90, U↕) /TR8ATCC(90, U↕||):x/ParCtrl . General parallel arrangement Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 287: Minimum Circulating Current (Mcc) Method

    A nominal value of 200 for Comp should be appropriate to achieve sensitive Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 288: Master Follower (Mf) Method

    Set the control mode to Manual for each transformer in the parallel control group Open the test display for Transformer Voltage Control on the LHMI in Main menu /Test/ Function status /Control/TransformerVoltageControl (90, U↕). Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 289: Completing The Test

    After the test is completed and relevant disturbance records are saved to document the test, go to Main menu /Clear on the local HMI and clear all LEDs, the process eventlist and disturbances from the IED. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 291: Checking The Directionality

    L1Dir = Forward • L2Dir = Forward • L3Dir = Forward The following will be shown if the load current flows in the reverse direction (importing): Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 292 Usually it is enough to look at the resistive values to get information of the load direction, that must anyway be compared with the indication given by external equipment measuring the same power flow. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 293: Commissioning And Maintenance Of The Fault Clearing System

    The periodicity of all tests depends on several factors, for example the importance of the installation, environmental conditions, simple or complex equipment, static or electromechanical IEDs, and so on. The normal maintenance praxis of the user should be followed. However, Hitachi Power grids' recommendation is as follows: Every second to third year •...
  • Page 294: Visual Inspection

    Hitachi Power grids protection IEDs are preferably tested by aid of components from the COMBITEST testing system described in information B03-9510 E. Main components are RTXP 8/18/24 test switch usually located to the left in each protection IED and RTXH 8/18/24 test handle, which is inserted in test switch at secondary testing.
  • Page 295: Self Supervision Check

    The neutral-point voltage to an earth-fault protection IED is checked. The voltage is normally 0.1 to 1V secondary. However, voltage can be considerably higher due to harmonics. Normally a CVT secondary can have around 2.5 - 3% third-harmonic voltage. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 296: Restoring

    Thus a list should be prepared of all items disturbed during test so that all can be put back into service quickly and without overlooking something. It should be put back into service item by item and signed by the responsible engineer. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 297: Troubleshooting

    No problem detected. None. Time synch Fail No time synchronization. Check the synchronization source for problems. If the problem persists, contact your Hitachi Power grids representative for service. Real time clock Ready No problem detected. None. Real time clock Fail The real time clock has Set the clock.
  • Page 298: Fault Tracing

    Ready (I/O module name) Fail I/O modules has failed. Check that the I/O module has been configured and connected to the IOP1- block. If the problem persists, contact your Hitachi Power grids representative for service. 15.2 Fault tracing IP8765-1 v1 15.2.1...
  • Page 299: Using Front-Connected Pc

    The information can only be retrieved from the Parameter Setting software package. The PC can be connected either to the port at the front or at the rear of the IED. These events are logged as internal events. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 300: Diagnosing The Ied Status Via The Lhmi Hint Menu

    The Hint menu is currently only available in English. All the entries are in English, regardless of which language is selected. The supported list of hints are as follows: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 301 LDCM rate (2M) is not supported The <firmware version> does not support 2M mode. Set the LDCM to 64k bit mode. Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 302 LDCM system frequency System frequency is different in local and remote end of LDCM link. Check the parameter FrequencySel at both ends. Table continues on next page Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 303: Hardware Re-Configuration

    IED and the IED is restarted with some part of the configuration still requiring the module. Moving a module in an IED from one position to another Procedure: Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 304: Repair Instruction

    M11764-10 v2 An alternative is to open the IED and send only the faulty circuit board to Hitachi Power grids for repair. When a printed circuit board is sent to Hitachi Power grids, it must always be placed in a metallic, ESD-proof, protection bag.
  • Page 305: Repair Support

    Repair support M11768-3 v4 If an IED needs to be repaired, the whole IED must be removed and sent to an Hitachi Power grids Logistic Center. Before returning the material, an inquiry must be sent to the Hitachi Power grids Logistic Center.
  • Page 307: Glossary

    Nations-sponsored standards body within the International Telecommunications Union. CAN carrier module CCVT Capacitive Coupled Voltage Transformer Class C Protection Current Transformer class as per IEEE/ ANSI CMPPS Combined megapulses per second Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 308 Dynamic random access memory Disturbance report handler Digital signal processor Direct transfer trip scheme Ethernet configuration tool EHV network Extra high voltage network Electronic Industries Association Electromagnetic compatibility Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 309 IEC 60870-5-103 Communication standard for protection equipment. A serial master/slave protocol for point-to-point communication IEC 61850 Substation automation communication standard Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 310 Local detection device Light-emitting diode LON network tool Local operating network Miniature circuit breaker Mezzanine carrier module Milli-ampere module Main processing module MVAL Value of measurement Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 311 A balanced serial interface for the transmission of digital data in point-to- point connections RS485 Serial link according to EIA standard RS485 Real-time clock Remote terminal unit Substation Automation Select-before-operate Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 312 TPZ, TPY, TPX, TPS Current transformer class according to IEC Transformer Module. This module transforms currents and voltages taken from the process into levels suitable for further signal processing. Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 313 Three times zero-sequence current.Often referred to as the residual or the earth-fault current Three times the zero sequence voltage. Often referred to as the residual voltage or the neutral point voltage Transformer protection RET670 Commissioning manual © 2017 - 2022 Hitachi Energy. All rights reserved...
  • Page 316 Hitachi Energy Sweden AB Grid Automation Products SE-721 59 Västerås, Sweden Phone +46 (0) 10 738 00 00 https://hitachienergy.com/protection-control Scan this QR code to visit our website © 2017 - 2022 Hitachi Energy. All rights reserved...

This manual is also suitable for:

Relion 670 series

Table of Contents