Description; Omd800 Switching Sequence; Line 1 Priority - ABB OMD800 Installation And Operating Instruction

Automatic control unit
Table of Contents

Advertisement

A U TO M AT I C C O N T R O L U N I T, O M D 8 0 0
3

Description

3.1

OMD800 switching sequence

3.1.1

Line 1 priority

The switching sequence of OMD800 can be summarized in following steps:
An anomaly occurs on the Line 1
Switching delay
Generator start
Delay on transfer
If Pre-transfer signal active:
Change-over switch (Switch I) to the position O
Dead band I to II delay
Change-over switch (Switch II) to the position II
If Pre-transfer signal active: Pre-transfer signal output off
And the back switching sequence can be summarized in the following steps:
The Line 1 will start the normal functioning
Back switching delay
If Pre-transfer signal active:
Change-over switch (Switch II) to the position O
Dead band II to I delay
Change-over switch (Switch I) to the position I
If Pre-transfer signal active:
Generator stop delay
Generator stop
LINE 1
LINE 2
Switch I status
Switch II status
Gen. START
Ts: Switching delay, Tt: Delay on transfer, Ds: Dead band I to II, TBs: Back switching delay, DBs: Dead band II to I, Gs: Generator stop delay
Figure 3.1
Automatic Switching Sequences in OMD800
Pre-trasnfer signal output on,
Pre-transfer I to II delay
Pre-transfer output on,
Pre-transfer II to I delay
Pre-transfer output off
Ts
Tt
Ds
TBs
DBs
Gs
9