Install AKD-10 Retrofill Breaker

• Ensure only qualified personnel install, operate, service, and maintain all electrical
equipment.
After the existing breaker is removed and the compartment modified, the pre-wired Retrofill breaker can now
be installed in the AKD-10 switchgear.
1. Verify that the breaker is in the disconnected and OPEN position before mounting it on rails.
2. Pull out the cubicle rails, horizontal to the ground.
3. The rails can now support and secure the Retrofill breaker in the switchgear.
4. For WavePro Retrofill Breaker (WPS-08, WPH-08, WPS-08, WPS-16, WPH-16, WPS-20): Insert eyebolts in
the eye bolt weld nuts as shown in Figure 7. Use a chain and hook to lift the breaker from above.
Use GE part number 0247B8961G002 lifting bar and suitable hoist to lift from above as shown in Figure 8.
EntelliGuard R Circuit Breaker Retrofill AKD-10 Installation Manual
19
• It must be ensured that the supply power to
Figure 8. AKD-10—Using GE Lifting bar and hoist
the compartment is turned off/
compartment is de-energized for all the
incoming and outgoing circuits of the LVS
prior to any work being conducted on it.
During the installation and related work on
the equipment, it must be ensured that the
operator is using the prescribed PPE for the
specified tasks.