Figure 4-6 Securing the equipment to the concrete platform
----End
Follow-up Procedure
After the equipment is hoisted and installed, verify the installation to ensure
normal use and smooth subsequent installation.
Table 4-6 Installation checklist
No.
1
2
3
Issue 04 (2022-06-30)
Check Item
Contact between
equipment and
concrete platforms
Maintenance door
Aerial work platform
Copyright © Huawei Technologies Co., Ltd.
Check Method
Observe.
Open and close each
door once.
Observe.
4 System Installation
Criteria
The equipment is in
close contact with
and evenly supported
by the concrete
platforms.
All doors can be
smoothly opened and
closed.
The aerial work
platform is prepared
based on site
requirements.