Huawei FusionModule500 User Manual page 139

Smart mini data center
Hide thumbs Also See for FusionModule500:
Table of Contents

Advertisement

FusionModule500 Smart Mini Data Center
User Manual
2.
3.
Issue 02 (2020-12-25)
Figure 4-88 Installing a cage nut
Install guide rails. Horizontally place a guide rail to the installation location
through the positioning block at the front of the guide rail and the
positioning hook at the rear of the guide rail. Fasten four M6 screws (two on
each side) to fix the front end and six M6 screws (three on each side) to fix
the rear end, as shown in the lower right figure.
CA UTION
Before installing a guide rail, check the (F/L, F/R) labels on the guide rail to
identify whether it is for the left or right and which part is the front or rear.
F/L indicates the front end of the left guide rail, and F/R indicates the front
end of the right guide rail.
Figure 4-89 Installing a guide rail
Install a filler panel for guide rails. Fasten the M6 screws to install the filler
panel for the guide rails.
Copyright © Huawei Technologies Co., Ltd.
4 Installation Guide
129

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents