Figure 4-6 Securing the PDC
----End
4.4.2 Installing the PDC on an ESD Floor
Context
A support is required when the PDC is installed on an ESD floor. The support height depends
on the height between the ground and the ESD floor.
Procedure
Step 1 Lower the anchor bots of the PDC using a wrench until all castors are off the ground and the
cabinet is level.
Step 2 Lift the PDC onto the support and align the mounting holes on the PDC with those on the
support.
Step 3 Level the PDC by adjusting the anchor bolts, as shown by (1) in
Step 4 Insert four M12 bolts into the mounting holes on the PDC and support. Partially tighten the
bolts, as shown by (2) in