Ground positions are designed on the right and left on the top of the PDC. Select either one based on the
position of the ground grid or busbar.
Step 3 Connect the input power cables to the mains output circuit breaker, N bar, and PE bar of the
PDC, as shown in
Figure 4-21 Installing input power cables
(1) Input I
Step 4 Connect the output cables to the customer terminal bar, N bar, and PE bar in turn, as shown in
Figure
Issue 01 (2016-02-27)
Figure 4-20 Installing a Ground Cable
Figure
4-21.
4-22.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
(2) Input II
4 Installation Guide
36