Start-up
Bosch Rexroth AG, MIT: LU 2, 3 842 358 814/2017-01
• Before initial commissioning ensure that there are no protruding or sharp-edged
parts that may endanger personnel working or moving in the area.
• According to EU Machinery Directive 2006/42/EC, you must equip the transfer
system with EMERGENCY STOP devices.
• The surfaces of engines and gearboxes can reach temperatures of over 65 °C under
certain load and operating conditions. In these cases, you must comply with the
appropriate design measures (protective measures) or the corresponding warnings
of the applicable accident prevention regulations (UVV)!
• Make sure that all electrical connections are either used or covered. Make sure that
all screw and plug-in connections are properly seated.
All relevant protective covers must be installed.
• Continuous conveyors which are in motion or in operation may only be inspected
and adjusted once all required safeguards are in place.
• Note EN ISO 13857 when you remove or replace safeguards and/or nullify a safety
guideline.
• Test runs with open panels are only allowed if they are carried out by a competent
person using tip switches and no interference through other switching elements exists.
• Only start up the product if all safety devices have been installed in the system
and are functional.
• Start up the product only if it is installed completely.
9.1.1

Short description commissioning

1.
Mount the drive to the oil container (see page 31)
2.
Set delivery volume (see page 15 and 18)
3.
Mount the drive with the oil container to the support bracket (see page 32)
4.
Connect connection cable (see page 32)
• After connecting the power cable and with supply voltage present, the LED
indicators fl ash green (GN) in 5s intervals.
• A fl ashing arrow icon
appears in the display.
• The lubricating unit is ready for operation with the parameters previously set.

9.2 Re-commissioning after a standstill period

Follow the steps for fi rst-time operation.