PROFINET
To create a project offline, you need the PROFINET address, the device type and the device
version, e.g. firmware version 4.5 or higher.
Create a new project
1. Call the "Project > New ..." menu.
The following default settings are displayed:
– User projects: Projects already in the target directory
– Name: Project_1 (can be freely selected)
– Type: Project
– Storage location (path): Default (can be set as required)
2. If necessary, correct "Name" and "Storage location", and confirm with "OK".
The project is created offline and loaded to the target system when the configuring is
complete.
STARTER Commissioning Manual
Commissioning Manual, (IH1), 07/2016, 6SL3097-4AF00-0BP5
3.4 Creating a project in the STARTER commissioning tool