84 Installation checklist
Check
The drive is grounded properly.
The mains (input power) voltage matches the drive nominal input voltage.
The mains (input power) connections at U1, V1 and W1 and their tightening torques are OK.
Appropriate mains (input power) fuses and disconnector are installed.
The motor connections at U2, V2 and W2 and their tightening torques are OK.
The motor cable is routed away from other cables.
Setting of the fan voltage transformer
There are no power factor compensation capacitors in the motor cable.
The external control connections inside the drive are OK.
There are no tools, foreign objects or dust from drilling inside the drive.
Mains (input power) voltage cannot be applied to the output of the drive (with bypass
connection).
Drive, motor connection box and other covers are in place.