Hitachi Relion 670 Series Commissioning Manual page 257

Line distance protection
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

1MRK506371-UUS Rev. M
ANSI07000188 V1 EN-US
Figure 56:
11.17
Basic IED functions
11.17.1
Parameter setting group handling SETGRPS
Prepare the IED for verification of settings as outlined in section
11.17.1.1
Verifying the settings
1.
Check the configuration of binary inputs that control the selection of the active setting group.
2.
Browse to the ActiveGroup menu to achieve information about the active setting group.
The ActiveGroup menu is located on the local HMI underMain menu/Test /Function status/
Setting groups /ActiveGroup
The ActiveGroup menu is located on the PCM600 under Main menu/Test/Function status/
Setting groups /ActiveGroup
3.
Connect the appropriate dc voltage to the corresponding binary input of the IED and observe the
information presented on the local HMI.
The displayed information must always correspond to the activated input.
4.
Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting groups are
described in the corresponding PCM600 documents and instructions for the operators within the
SCS are included in the SCS documentation.
Line distance protection REL670
Commissioning manual
Test of RTC with I/O
© 2017 - 2023 Hitachi Energy. All rights reserved
Testing functionality by secondary injection
"Preparing for test"
in this chapter.
Section 11
SEMOD52026-1 v1
M11369-2 v4
M11369-4 v5
251

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion rel670

Table of Contents