上电前检查 、上电调测
11
Checking Before Power-On and Performing Power-On Commissioning
上电前检查/Checking Before Power-On
检查项
操作方法
参考依据
线缆整齐、美观,余长要剪除,不能盘
绕。
电源线与信号线之间距离必须大于20mm。
电源线长度方向需进行线缆绑扎,绑扎
间隔不超过200mm,较粗的电源线绑扎
间距可适当放大。
线扣无重叠,接头剪齐,无尖刺外露等
查看线缆连接。
线缆连接
查看线缆布放。
现象。
在转弯处按要求留出余量,不得拉紧。
查看线缆标签。
走线平直、顺滑,机柜内电缆无交叉。
线缆紧固牢靠。
参见供配电系统图查看
空开标签正确、清晰、完整,无脱落。
空开标签。
开合一次空开,确保空
开能够正常的合上、断
空开状态
各负载空开处于安全可控状态。
开。
所有配电柜、配电箱和配电盒上的空开处于
查看空开状态。
"OFF"状态,所有防雷空开处于"ON"状态。
用相序表查看预制模块
上下级配电设备相序一
相序
相序一致。
致性。
检查蓄电池数量。
蓄电池数量正确,蓄电池外观完好无损。
查看蓄电池连接。
蓄电池连接符合设计,蓄电池极性连接正确,
安装牢固可靠。
蓄电池
万用表测量蓄电池单体
电压值在蓄电池额定电压范围内,
电压。
电池组的电压=单个电池电压×电池节数。
电压值满足系统备电的电压范围。
万用表测量蓄电池组电
压。
器件安装位置与监控器件布局图一致,
且安装牢固可靠。
器件安装
查看监控器件的安装和
线缆连接正确。
连接
连接。
消防气瓶压力表指针在表盘绿区。
器件安装
消防气瓶上的保险销完好无损,无遗失。
查看消防器件的安装和
和线缆连
线缆连接正确、牢固可靠。
线缆连接情况。
接情况
器件安装位置与照明器件布局图一致。
器件安装
查看照明器件的安装和
线缆连接正确。
连接
连接。
安装消防设备
06
Installing
Item
Method
Criteria
Check the cable connection.
Connecting
Check the cable layout.
cables
Check the cable labels.
Verify the circuit breaker labels by
Circuit breaker labels are correct, clear, complete,
referring to the power supply and
and attached properly.
distribution system diagram.
Verify that circuit breakers can be
Ensure that all load circuit breakers are reliable and
smoothly switched on and off.
controllable.
Circuit breaker
status
All power distribution frame (PDF), power distribution
box (PDB), and power distribution unit (PDU) circuit
Check the circuit breaker status.
breakers are in the OFF state, and all surge
protective device (SPD) circuit breakers are in the
ON state.
Verify that the phase sequences of
the upstream and downstream
Phase
power distribution devices are
The phase sequences are consistent.
sequence
consistent using a phase sequence
meter.
Check the number of batteries.
The batteries are correct in quantity and intact.
Batteries are connected according to the design
Check battery connection.
requirements and installed securely. Battery
electrodes are correctly connected.
The voltage measurement result is within the rated
Battery
Measure the battery cell voltage
battery voltage.
using a multimeter.
Battery string voltage = Voltage of a single battery x
Number of batteries
Measure the battery string voltage
The voltage measurement result meets the
using a multimeter.
requirement of system power backup.
Device
installation
Check the monitoring device
and
installation and connection.
connection
Device
installation
Check the fire extinguishing device
and cable
installation and cable connections.
connections
Device
installation
Check the lighting device
and
installation and connection.
connection
Cables are neat, tidy, not coiled, and excessive
parts are cut.
Power cables are at least 20 mm away from
signal cables.
Power cables are bound at a spacing of at most
200 mm. For thicker cables, the spacing can be
greater.
Cable ties do not overlap, and the joints are
evenly cut without burrs.
Cables are placed properly and not tense at
turning points.
Cable routes are straight and smooth, and do
not intersect inside a cabinet.
Cables are securely bound and connected.
Step 1 Switch on the external input circuit breaker.
Step 2 Switch on the power circuit breakers and power on the devices one by one by referring to
the power supply and distribution system diagram.
Step 3 Check the initial configuration parameters of the device.
Devices are installed securely as shown in the
monitoring device layout diagram.
Cables are correctly connected.
The pressure pointer of the fire cylinder is in the
green zone.
The safety pin on the fire cylinder is intact and
properly installed.
All cables are correctly and securely connected.
Devices are installed in positions shown in the
lighting device layout diagram.
Cables are correctly connected.
上电调测/Checking Before Power-On
步骤1:合上外部输入空开。
步骤2:参见供配电系统图,合上电源空开,逐级给对应设备上电。
步骤3:核对设备初始配置参数
设备型号
调测内容
根据现场实际配置设置电池接入、额定容量BLVD使能、安装时间和电压不平衡
TP电源系统
检测模式等参数
温控
设置制冷设定点、制冷回差等。
ECC800
1、准备和登录Web。
2、检查系统类型和设置微模块名称
3、设置和添加设备:TP电源,COM口连接设备,AI/DI模块,第三方设备等。
4、检查监控器件连接情况。
5、设置CIM参数,BIM和CIM组网(选配)
1、IP地址域安装规划。
2、获取NetEco软件License。
3、设备上电。
4、加载License。
5、配置设备和NetEco安全。
6、登录NetEco客户端。
NetEco(选配)
7、创建管理域。
8、添加集装箱。
9、调测摄像机和VCN。
10、设置和添加ECC800。
(1)使用网线连接ECC800的WAN_1接口。
(2)设置NetEco网管参数。
(3)在NetEco上创建ECC800采集器。
Device Model
Item
TP power
Set parameters such as battery connected, rated capacity, battery low voltage
system
disconnection (BLVD) enabled, installation time, and voltage imbalance
detection mode based on site requirements.
Temperature
Set the cooling threshold and cooling hysteresis.
control
ECC800
1. Prepare and log in to the WebUI.
2. Check the system type and set the smart module name.
3. Set and add a device: TP power supply, device connected to a COM port,
AI/DI module, and third-party device.
4. Check the monitoring device connection.
5. Set CIM parameters, and (optional) configure BIM and CIM networking.
1. Plan the IP address domain.
2. Obtain the NetEco software license.
3. Power on the device.
4. Load the license.
5. Configure the device and NetEco security.
6. Log in to the NetEco client.
(Optional)
7. Create the management domain.
NetEco
8. Add a ContainerDC.
9. Commission cameras and VCN.
10. Set and add the ECC800.
(1) Connect the communications cable to the WAN_1 port on the ECC800.
(2) Set NetEco parameters.
(3) Create an ECC800 collector on the NetEco.
Copyright © Huawei Technologies Co., Ltd. 2020. All rights reserved