10. Installation

Module installation

Over 100
Front side
<Case 1>
Over 100 Over 100
Front side
Over 100
Over 100
Front side
❇ For <Case 1> or <Case 3>
• Height of the wall on the front side should not be
higher than 1500mm.
• Height of the wall on the air inlet side should not be
higher than 500mm.
• Height of the wall on the side is not limited.
• If the height of the wall exceeds by certain value (h1, h2),
additional clearance [(h1)/2, (h2)/2 : Half of the exceeded
distance] should be added to the service space (S1, S2).
S1+h1/2
Over 100
Over 100
Over 100
Over 100
<Case 3>
(Unit : mm)
S2+h2/2
Over 300
Front
Over 400
side
<Case 2>
❇ At Machinery Room
• Make sure to install both discharge duct and suction
grille / louver
• Static pressure of the discharge duct should be within
the standard specification (78.45Pa) when installing
the duct.
• Secure enough cross-sectional area on grille
surface for easy air intake in case of machinery room
installation.
Ex.) Mechanical room
Height of
the wall is
unlimited
Over 400
Discharged air
Discharged air
Grille/louver
Grille/louver