Transport and Storage
LSA Control S.L. www.lsa-control.com comercial@lsa-control.com (+34) 960 62 43 01
Cables and Connectors
Bearing time / months
Measures for commissioning
> 1
> 12
> 60
●
●
●
Control all parts to be free of damage.
●
●
Check all electrical contacts to be free from corrosion.
Visually inspect the cable jacket. Do not use the cable if you de‐
●
tect any abnormalities (squeezed or kinked spots, color devia‐
tions, ...).
Tab. 6-6:
Measure before commissioning cables and connectors that have been
stored over a prolonged period of time
PGM
Bearing time / months
Measures for commissioning
> 9
> 24
> 60
Let the internal gear pump in its delivery state (moistened with
●
●
●
mineral oil)
●
●
Fill the internal gear pump with mineral oil
Before mounting, check the complete internal gear pump for dam‐
age and corrosion.
At a test run, check the internal gear pump for functionality and
leakproofness.
●
In the case of a storage time > 24 months, change the shaft seal‐
ing ring.
After the maximum storage time we recommend a preventive
check of the internal gear pump with change of the sealings by
the responsible Rexroth service!
Tab. 6-7:
Measures before commissioning pumps that have been stored over a
prolonged period of time