Step 2 Route AC output power cables through the protective board at the bottom of the subrack.
Step 3 Secure the AC output power cables to corresponding AC output circuit breakers and
terminals.
Figure 4-13 Installing AC output power cables
(1) AC load
----End
4.10 Installing 220/380 V AC Three-Phase, Four-wire Input
Power Cables
Procedure
Step 1 Route 220/380 V AC three-phase, four-wire input power cables through the protective board
at the bottom of the subrack.
Step 2 Secure the AC input power cables to corresponding AC input circuit breakers and terminals,
as shown in
Issue 05 (2020-04-07)
Figure
4-14.