Lifting; Tools Used For Lifting - ABB PVS-100 Series Hardware Manual

Solar inverters medium voltage compact skid
Hide thumbs Also See for PVS-100 Series:
Table of Contents

Advertisement

Lifting

WARNING!
Inspect the container before any activity. Make sure that the container has no
protuberance, enough rings and is in good condition. Ignorance of this message
can cause physical injury, death or damage to the equipment.
Before lifting the MVCS, follow these instructions.
Protect the corners of the MVCS against shock.
The minimum rated loading capacity of each sling is eight tons.
The minimum length of each sling is five meters.
Adjust the length of lifting slings so that the MVCS does not tilt during lifting.
Do not allow the lifting slings to scratch the walls or roof. Damaged paint can lead to
corrosion.
Use a guide wire attached to a lower corner of the MVCS to prevent rotation.

Tools used for lifting

20 tons bridge crane
four slings
minimum loading/unloading area = 20 x 3 meters
Storing, lifting and transporting 31