[VII Test run check lists for initial work and expansion work]

[2] Test run check list

Before performing a test run
Be sure to complete the test run on the air-conditioning units before performing the test run check of the AE-200/AE-50/EW-50.

1. Test run check sheet

About the test run check sheet
After configuring the settings in "Setting check list" on the previous page, check the items in (1) to (3) below in accordance with the test
procedure of the test run check list on the next page.
(1) Startup check
・ After the settings of the initial screen are finished, switch to the management screen.
・ Check that the screen displayed during startup is displayed.
・ The startup time differs depending on the number of air-conditioning units connected but the startup should complete after
about 5 minutes.
・ Check the display of each floor and confirm that an error is not occurring.
・ If an error has occurred, check the error history in the history screen and remove the cause of the error.
(2) ON/OFF operation from the AE-200/AE-50/EW-50
・ Operate the air-conditioning units from the AE-200/AE-50/EW-50.
・ Confirm that the air-conditioning units are operating by checking the display on the local remote controllers.
・ Perform operation of the air-conditioning units in the order of group, block, floor, and entire building.
・ If different air-conditioning units and general equipment were operated by performing operation from the
AE-200/AE-50/EW-50, check the following settings.
→ Group settings (Refer to "8-2-7. Group settings" in AE-200/AE-50 Instruction Book or AE-200/AE-50/EW-50
Instruction Book (Web Browser for Initial Settings).)
→ Block settings (Refer to "8-2-9. Block settings" in AE-200/AE-50 Instruction Book or AE-200/AE-50/EW-50 Instruction
Book (Web Browser for Initial Settings).)
→ Floor layout settings (Refer to "8-2-10. Floor layout" in AE-200/AE-50 Instruction Book.)
(3) Local remote controller ON/OFF
* Do not perform this check when there are no local remote controllers connected.
・ Operate the air-conditioning units from the local remote controllers.
・ Check that the air-conditioning units operate on the AE-200/AE-50 unit. Perform the check with the Web browser in the
case of the EW-50.
・ Check with the display of the AE-200/AE-50 set to the floor screen, block screen, and entire building screen. Perform the
check with the Web browser in the case of the EW-50.
To make the check sheets easy to read, fill in the information for just one installation floor or one AE-200/AE-50/EW-50 unit on each
check sheet.
○ Save a backup of the setting data of the AE-200/AE-50 after the test run.
NOTE:
For the backup procedure, refer to "9-1. Backing up the data to a USB memory device" in "AE-200/AE-50 Instruction
Book."
For the backup procedure for the EW-50, refer to "Instruction Book (Web Browser for Initial Settings)."