Releasing The Function To Be Tested - Hitachi Relion SAM600 Commissioning Manual

Switchgear control unit
Table of Contents

Advertisement

Section 8
Testing IED operation
IEC09000652 V1 EN-US
Figure 12:
8.5

Releasing the function to be tested

Release or unblock the function to be tested. This is done to ensure that only the function or the
chain of functions to be tested are in operation and that other functions are prevented from operating.
Release the tested function(s) by setting the corresponding Blocked parameter under Function test
modes to No in the PCM600.
When testing a function in this blocking feature, remember that not only the actual function must be
activated, but the whole sequence of interconnected functions (from measuring inputs to binary
output contacts), including logic must be activated. Before starting a new test mode session, scroll
through every function to ensure that only the function to be tested (and the interconnected ones)
have the parameters Blocked and eventually EvDisable set to No and Yes respectively. Remember
that a function is also blocked if the BLOCK input signal on the corresponding function block is
active, which depends on the configuration. Ensure that the logical status of the BLOCK input signal
is equal to 0 for the function to be tested. Event function blocks can also be individually blocked to
ensure that no events are reported to a remote station during the test. This is done by setting the
parameter EvDisable to Yes.
Procedure
1.
Click the Function test modes menu.
40
IL1
IL2
IL3
IN
UL1
UL2
UL3
UN
IEC 61850
Connection example of the test equipment to the IED when test equipment is
connected to the transformer input module
In order to get the following information in SAM600-IO, the LHMI service kit is need. For
more information on LHMI service kit, refer section User interface.
Any function is blocked if the corresponding setting in the local HMI under Main menu /
Test /Function test modes menu remains On, that is, the parameter Blocked is set to
Yes and the parameter TESTMODE under Main menu/Test /IED test mode remains
active. All functions that were blocked or released in a previous test mode session, that
is, the parameter Test mode is set to On, are reset when a new test mode session is
started.
© 2017 - 2023 Hitachi Energy. All rights reserved
IL1
IL2
IL3
IN (I4,I5)
UL1
UL2
UL3
UN
UN (U4,U5)
TRIP L1
TRIP L2
TRIP L3
IEC09000652-1-en.vsd
1MRK511447-UEN Rev. E
Switchgear control unit SAM600-IO
Commissioning manual
M11413-2 v8

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion sam600-io

Table of Contents