LIFTING AND MOVING

(No more than 8 modules stacked)
WARNING:
Check that the ground on which the staircase Escalib is to be erected is able to withstand the load.
WARNING:
Comply with the general rules for handling and stability.
REQUIREMENTS:
> Fit new anchorages as new
modules are added.
> The dismantle must be done in
the reverse order of assembly.
1 - Reposition the guardrails to close
any side exits. Check that the M24
screws are tight in place. Attach the
crane hooks to the 2 lifting rings.
Detach the anchors.
4 - Anchor the Escalib
before removing the
slings from the crane.
7 - Fill the Pre-Use Inspection Report
9
WWW.COMBISAFE.COM
2 - Move the Escalib. Pivot the Escalib
according to the height of the level
which needs to be accessed with 90°
rotations; Install 8 cm away from the
wall.
5 - At the access levels, the
guardrails are positioned so as to
privilege access by the main face A
(face names shown on the sticker).
3 - Positioning on the ground and
leveling the Escalib.
6 - Check that the stair tower has
been anchored before unhooking
the slings. Guardrails must be
swung out of the way to allow
access to the required level.