Max. Stroke
Min. Stroke
Loosen locknut to
adjust plunger stroke
FiguRe 15
Typical lubricator pump with plunger shown at max stroke/flow
Screw plunger out of the base to increase stroke/flow, or in to
Leave at least 4 plunger threads engaged in the base at max
New Compressor Start-up
Follow these steps to start-up the compressor:
1.
Pre-lube the compressor frame before startup.
2.
Set the adjustment on the lubricator pump plunger to the maximum output
position.
3.
Start the compressor and operate for about 30 minutes allowing the oil to
warm up.
4.
Check for proper lubricator performance by monitoring the cycle indicator or
other oil flow measurement device.
decrease stroke/flow.
Complies with ANSI Z535, ISO 3864, OSHA 1910.145 (f) (9)
stroke.
Complies with ANSI Z535, ISO 3864, OSHA 1910.145 (f) (9)
H301/302 HSR Compressors | Rev. 2.2 | 77