Install the Bay and Backplane Connections
If you want to install wide CRMS and have 600-mm (23.6-in.) kick plates installed, complete the
Step 3
"DLP-E121 Replace the Existing 600-mm Kick Plates with 900-mm Kick Plates" task on page
Step 4
If you want to install the wide CRMs, complete the
page
Step 5
Continue with the
Stop. You have completed this procedure.
NTP-E4 Install the Bay Power and Ground
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Warning
This product requires short-circuit (overcurrent) protection, to be provided as part of the building
installation. Install only in accordance with national and local wiring regulations. Statement 1045
78-17203-01
17-34.
"NTP-E4 Install the Bay Power and Ground" procedure on page
This procedure explains how to install power feeds and ground the
ONS 15600.
7/16-inch nut driver or socket
9/64-inch Allen wrench
Power cable, rated for at least 125-A capacity
Ground cable, rated for at least 125-A capacity
Listed pressure terminal connectors such as ring and fork types; connectors
must be suitable for the chosen cable
Wire cutters
Wire strippers
Crimp tool
Screwdriver
Nuts (4)
Two-hole power lugs, 0.625-inch hole spacing; 0.25-inch bolt holes
(Panduit LCCF2-14AZFW-E) (for underfloor-routed power cables) (16)
Under-floor power kit (800-23062-XX) (optional):
NTP-E2 Install the Bay Assembly, page 1-5
NTP-E3 Open and Remove the Front Door, page 1-6
Required
Onsite
None
"DLP-E143 Install the Wide CRMs" task on
Screws (#8 x 0.75 inch) and washers (12)
Screws (#8 x 0.375 inch) and washers (8)
Power conduits (2)
Cable strain-relief brackets (2)
NTP- E4 Install the Bay Power and Ground
1-9.
Cisco ONS 15600 Procedure Guide, R7.0
17-20.
1-9