Installing the Cable-Management Bracket
The cable-management bracket attaches to the interface processor end of the chassis just above the
card cage and below the blower module. (See Figure 8.) Use the bracket to keep network interface
cables untangled and orderly, and to prevent cables from hindering access to interface processors in
the interface processor slots.
Install the bracket before connecting network interface cables to the interface processor ports;
otherwise, you will probably need to disconnect the cables to install the screws that secure the
brackets. Route interface cables through the bracket as you connect them to the interface processor
ports.
Tools and Equipment Required
You will need the following tools and parts to install the cable-management brackets; brackets and
pan head screws are included with the chassis:
Large flat-blade screwdriver
One cable-management bracket and two slotted pan head screws (already attached to the chassis)
Installation Procedure
To install the cable-management bracket on the router, follow these steps:
Step 1
Figure 8
Blower
module
Loosen
screws (2)
Bracket
Card cage
On the interface processor end of the chassis, locate the two slotted screws positioned
below the blower module and above the card cage. (See Figure 8.)
Cable-Management Bracket
Cisco 7513 and Cisco 7576 Chassis Replacement and Upgrade Instructions
Installing the Cable-Management Bracket