9.2 Work Items, Work Assignment, and Work Time
"Table 9.2" lists the work items, standard work time, and the person in charge of these types of work.
Work item
Checking the delivered items
Installing option
Verifying operation
Preparation of handing over to
the System Administrator
Handover to the system administrator
SET0903000
9.3 Procedure for Installing SSD SFF
SET0903010
9.3.1 Checking the delivered items
(1) Check the delivered items by confirming the following.
1. The types and quantities of delivered options match those written on the order sheet.
2. The delivered items match those listed in the List of Accessories.
3. All cabinets are free of any abnormalities such as scratches, dents, or dirt.
4. The specifications and version level of units delivered separately due to delivery considerations
are available for the target functions.
(2) Proceed to
SET0903020
9.3.2 Installing option
Install according to the following procedures.
ANNT)
- The installation location and quantity have to indicate by the system administrator.
(1) Remove the dummy of SSD SFF out of the DU_PCIE.
(2) Install the SSD SFF into the DU_PCIE.
(3) Turn on AC power of the Base Unit when the Base Unit state is "AC Power Off".
→ Wait until green indicator of the "System Power" turns off.
(4) Make sure that orange indicator of the "System Alarm" and "CSS" are not lit or blinking.
(See "Figure 9.3.2".)
"9.3.2 Installing
option".
Table 9.2
Person in charge
Service engineer
Service engineer
Service engineer
Service engineer
System administrator and
Service engineer
62
Work time
(minute)
5
5
15
1
5