Site Preparation Checklist
Table G-1
Task No. Planning Activity
1
2
3
4
5
6
1. Verify that the power supply installed in the chassis has a dedicated AC source circuit.
2. UPS = uninterruptible power supply.
Cisco Nexus 2000 Series Hardware Installation Guide
G-2
Site Planning Checklist
Space evaluation:
Space and layout
•
Floor covering
•
Impact and vibration
•
Lighting
•
Maintenance access
•
Environmental evaluation:
Ambient temperature
•
Humidity
•
Altitude
•
Atmospheric contamination
•
Air flow
•
Power evaluation:
Input power type
•
1
Power receptacles
•
Receptacle proximity to the
•
equipment
Dedicated circuit for power supply
•
Dedicated (separate) circuits for
•
redundant power supplies
2
UPS
for power failures
•
Grounding evaluation:
Circuit breaker size
•
CO ground (AC-powered systems)
•
Cable and interface equipment
evaluation:
Cable type
•
Connector type
•
Cable distance limitations
•
Interface equipment (transceivers)
•
3
EMI
evaluation:
Distance limitations for signaling
•
Site wiring
•
4
RFI
levels
•
Appendix G
Site Preparation and Maintenance Records
Verified By
Time
Date